        The site has been identified on Noosa Shire Councils Potential and Actual Acid Sulphate Soils Overlay Map. As the proposed
        development is to undertake filling and excavation below RL20.0m AHD, it is anticipated that Acid Sulphate Soils may be
        encountered. Therefore, it is recommended that an Acid Sulphate Soil investigation be completed as part of the detailed
        geotechnical investigation conducted for the site. If Acid Sulphate Soils are present, then an Acid Sulphate Soil Management
        Plan will be required.


        All earthworks will be undertaken in accordance with the Noosa Shire Council guidelines.


3.3     ROADWORKS

        The proposed road works are as follows:

            −    Three new driveway crossovers are proposed from the private access road into Lot 3, to provide vehicle access to
                 the basement carpark, ground-level carpark, and loading docks. Two new driveway crossovers are proposed from
                 the private access street into Lot 7, to provide vehicle access to the surface carparking and loading docks;

            −    Multiple pedestrian entrances into both Lot 3 and Lot 7 are proposed along the private access roadway;

            −    A pedestrian walkway is proposed along the existing pedestrian access easement along the western side of Lot 3,
                 which will connect with a new pedestrian bridge that spans across the environmental zone and natural drainage
                 channel between the Lot 3 development and the existing shopping centre to the west; and

            −    All proposed road works will be undertaken in accordance with Noosa Shire Council Guidelines.

        Refer to the engineering drawings in Appendix B for further information.


3.4     SEWER

3.4.1   Existing Infrastructure

        The Unity Water As-Constructed Plans of the surrounding area indicate the following existing sewer reticulation information:

            −    An existing 225mm dia. sewer main is located below the western verge of the private access roadway at the southern
                 boundary of both development sites; and

            −    There are two existing 150mm dia. capped property connections into both Lot 3 and 7 respectively, with the Lot 3
                 property connection running below the existing private access roadway to the eastern verge.

        The Unity Water As-Constructed Plans of the existing sewer infrastructure can be found in Appendix C of this report.


3.4.2   Proposed Infrastructure

        The proposed sewer infrastructure for this development is as follows:

            −    It is proposed to construct two new property connections into the existing maintenance hole to service both Lot 3
                 and Lot 7 sites, which suit the internal development layout and driveway crossover placement;

            −    The existing property connection into Lot 7 is to be decommissioned, whilst the existing property connection into
                 Lot 3 is to remain to allow for future development of the area to the south of the Lot 3 development; and

            −    As the surrounding roadways and services have been master-planned to service a fully developed catchment, it is
                 expected the existing sewer infrastructure has sufficient capacity to service the proposed development.

        Refer to Appendix B for preliminary drawings of the proposed sewer works.




                                                   www.bornhorstward.com.au                                                     Page 6

Used in these records

About this file

File size
21.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 5 - Servicability Report.pdf · 21.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.