GENERAL COMMITTEE MEETING AGENDA 12 January 2015
Street Identification
5. The street address of the development must be clearly visible and discernible from
the primary frontage of the site by the provision of a street number and, where
appropriate, the building name.
Building Appearance
6. All air conditioning units or other mechanical equipment must be fully enclosed or
screened such that they are not visible from the street frontages nor adjoining
properties.
Water & Sewer Connections
7. An underground connection to reticulated water and sewerage must be provided to
the development site in accordance with the standards and requirements of Northern
SEQ Distributor–Retailer Authority (Unitywater).
8. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to the development site.
Landscaping
9. The development site must be landscaped. The works must be undertaken in
accordance with The Noosa Plan, Planning Scheme Policy PSP03 Landscaping
Plants and Guidelines and the approved plans.
10. Dense screening vegetation must be provided for the full length of the black PVC
chainlink fence and the bin enclosure along the Rene Street frontage.
11. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures
healthy, sustained and vigorous plant growth. All plant material must be allowed to
grow to full form and be refurbished when its life expectancy is reached.
12. All landscape works must be maintained generally in accordance with the approved
design for the life of the development.
Site Access and Driveways
13. A sealed access driveway must be provided from the common property road to all
parking and manoeuvring areas of the development. The works must include in
particular a driveway crossover in accordance with IPWEAQ standard drawing SEQ
R- 051 or R-052
Car Parking
14. A minimum of 17 car parking spaces must be provided and marked on the site. The
car parking must be made available and accessible at all times while the use is open
for business. The works must include in particular:
a. carspaces 1-5 and 12-15 must be allocated as staff parking spaces
b. 1 disabled parking space within the total
c. crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities
d. wheel stops for carspaces 7-12 to prevent vehicles entering the biobasin. The
wheel stops must be designed and installed in accordance with
AS/NZS2890.1:2004.
15. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
16. Directional signage must be provided to direct visitors and customers to the car
parking spaces provided on site.
Page 55 of 147
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.