2021-01-18 GC - Item 7 - Attachment 1 - Pathways and Boardwalks Asset Management Plan

of 34

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
7.    Levels of Service - The current levels of service for pathways and boardwalks is to support
      the services that are operated from or within these assets to the Noosa community. Council’s
      pathways and boardwalks assets are designed and constructed to suit the function of the
      service being provided which determines the levels of service. The measurement of these
      levels is ongoing, to monitor if the assets are either under or over serviced. The levels of service
      that have been developed in Section 2.9 of this document serve the purpose of how the
      pathways and boardwalk assets will be managed into the future. In addition, as result of
      adopting the service levels defined in Section 2.9, the annual service levels catalogues that
      are prepared for budget must be updated to reflect these activities and levels of service.
8.    Maintenance Plans – must be regularly reviewed and incorporated into the annual budget
      process and aligned to the levels of service activities defined in Section 2.9. Continued
      inspections and recording of asset condition and maintenance activities are key to achieving
      this initiative. This will be a key outcome for the Pathways and Boardwalks Working Group to
      develop site specific maintenance plans and develop the pathways and boardwalks
      maintenance plan for all the assets considered in this AMP.


7.3    Monitoring and Review Processes for the Asset Management Plan
This first edition of AMP for the pathways and boardwalks refers to current levels of services that
have existed over recent years. This AMP is to be a ‘living’ document reflecting actual practices used
in managing the pathways and boardwalks. In accordance with this, Council will balance cost, risk
and performance needs for the pathways and boardwalks.

The AMP will have a high-level annual review for developing the annual budget from the
maintenance and renewal plans. A full document review will occur on a four-year cycle, in line with
the completion of detailed condition assessments and the financial asset revaluation of the pathways
and boardwalks assets.


7.4    Asset Management Effectiveness
The effectiveness of this AMP will be measured in terms of:
1.   Adoption of the pathways and boardwalks AMP by Council.
2.   The ongoing development of good asset knowledge through a commitment to recording
     information against assets and undertaking cyclic condition assessments at the facility.
3.   Maintenance and renewal plans that are robust and initiate the annual budget process.
4.   Historical asset activities that are recorded and located in Council’s asset management
     system.
5.   Limited reactive work and more planned maintenance activities.
6.   The pathways and boardwalks AMP becomes the reference point for all information and
     enables good decision making for asset related activities and investments.
7.   Documented levels of service that complement the pathways and boardwalks assets that
     support the services provided by Council.




Asset Management Plan: Pathways and Boardwalks                                                   Page 25
Log in to download the original file

2021-01-18 GC - Item 7 - Attachment 1 - Pathways and Boardwalks Asset Management Plan(PDF, 2MB).pdf · 2.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.