Exposure to injury 5 Designers/consultants are to provide to the project team a And Project Manger
Structures
due to change in documented design risk assessment addressing the issues Designers
WA Code Of
design described above; Practice Consultants
- Hutchinson Builders Design Risk Assessment Form (HB- 2008
Exposure to injury
HSEQ-F-023-A) may be used as a minimum for a design Safe Design
due to change in Of Structures
risk assessment
Plant/equipment TAS Code Of
5 Regular meetings to be scheduled with designers/consultants Practice Project Manger
design
to review and where possible close out action/issues raised in 2012 Designers
the design risk assessment
5 Construct Only Project Client
Consult with the client to identify if there has been a design Project Manger
risk assessment been carried out for the project;
- If one is provide by the client - then review and any new
constructability hazards can be transfer to the Project
Risk Assessment
5 Where a design risk assessment is not provide by the client, Project Manger
the H&S implication for construction shall be managed as per Site Manager
the identified hazards identified in Hutchinson Builders Project Foreman
Risk Assessment and Risk Assessment Procedure MP:10
5 Where there are design changes in relation to both Design & Project Manger
Construct and Design Only projects the site team is to Site Manager
undertake a preliminary assessment and; Foreman
- Record yes or no on the project variation register to
identify if the changes may impact on the site health and
safety that involve change in;
New construction materials
Construction processes
Construction techniques previously used
Introduction of new hazardous materials
Amend or develop a new work method statement
for the change being made
5 Where YES has been recorded on the variation register the site Project Manger
team is to undertake a design changes assessment using; Site Manager
- Hutchinson Builders form HB-HSEQ-F-023-A Design Foreman
Change Risk Assessment
5 Results of the design change risk assessment are to be Project Manger
communicated to the relevant subcontractors or employees Site Manager
and involve a tool box talk to inform the relevant workers Foreman
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.