Fix a caution or danger safety sign to advise of electrical
hazard;
Be singularly identifiable through either numbering,
lettering or a combination of the two;
Have live parts protected to prevent contact by anyone
connecting or disconnecting plugs;
Have an insulated anchorage tie bar provided if there are
power points on the board to prevent straining on the
cable going into the power supply;
Have an insulated slot in the base for leads to go through
and a sign fitted to it stating “keep closed – run all leads
through bottom.”
5 Switchboards will have at least 1m clearance provided in front Site Manager /
of the switchboard. Subcontractor
3 All power circuits will be isolated and secured upon Site Manager /
completion of the work shift / when the site is unattended. Subcontractor
(This doesn’t apply to circuits supplying security lighting,
essential equipment or to locked relocatable structures).
5 Portable RCDs will be tested by the user before each use on a Site Manager /
daily basis and undergo an operating time at tripping current Subcontractor
test using an RCD tester carried out by a licenced electrician
every 3 months.
5 Fixed RCDs will be tested by a licenced electrician every month Site Manager /
by the operation of the pushbutton and undergo an operating Subcontractor
time at tripping current test using an RCD tester carried out by
a licenced electrician every three months from the time of
installation.
5 Work on site will be undertaken within the safe approach Site Manager /
distances (i.e. exclusion zones) and special provisions will be Subcontractor
made including:
a) to notify and obtain written permission from the power
authority before commencing work;
b) Not to commence work until a pre-start site meeting, a
risk assessment detailing the necessary controls to be
implemented and training has been completed.
All isolations of live electrical circuits will involve placing a Electrical
3 physical lock and attachment of a Danger tag with relevant Subcontractor
details associated with the isolation (including the name of the Site Manager
electrician who has undertaken the isolation) to prevent
5 unauthorised access.
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.