Repetitive lifting 4/ Wherever practicable, all objects will be designed, 2011 QLD,
Hutchinson Builders/
NSW & SA
5 constructed and purchased to enable safe manual handling. Subcontractor
Manual
5 Subcontractors to provide SWMS for high risk manual tasks on Handling
2000 VIC
Subcontractor / HSO
site. The SWMS is to address (as applicable):
Manual
- manually handling excessive loads Tasks 2010
- adopting poor postures when undertaking manual WA
handling tasks Hazardous
- repetitive lifting Manual
Tasks 2012
2 Mechanical equipment will be used for manual handling tasks Subcontractor / HSO
TAS & NT
wherever practicable on site.
5 Material delivery will be organised to enable unloading onsite Subcontractor / HSO
and to minimise manual handling.
5 Persons using mechanical equipment provided will be trained Subcontractor / HSO
in the safe use of that equipment and records kept.
B 4 E21 5 Hoist contractor/supplier to provide safety plan and Safe Work WHS Act Site manager /
Man/ Hoist Collapse
☐ Material Hoist electrical Methods on the safe set up, erection, servicing and
2011
WHS Reg
foreman /
Hoist failure dismantling of the hoist 2011 Parts subcontractor
5,6
Falling objects 5 A commissioning report must be provided to the site Site manager /
manager/foreman by a competent person certifying that the VIC OHS Reg
foreman / Operator
2007 Part
hoist is safe for common use before the hoist may be used 3.5, sch 3. / Subcontractor
onsite. AS 1418.1-
5 2002 Cranes Site manager /
Any operators must hold the appropriate licence and be hoists and foreman / Operator
winches
competent to operate the height and type of hoist installed. general
/
requirement Subcontractor
5 Evidence of the operator’s licence will be provided to s
Operator / HSO at
Hutchinson Builders, and copies made and retained on site Induction
(where copy facilities are available).
5 All services and repairs carried out on the hoist are to be Site Manager /
carried out by competent persons and all records recorded in foreman / Operator
the hoist log book. / competent person
B 5 E24 5 A review of the profile of the building will be carried out to WH&S Act Site manager /
☐ Mast Climber Mast collapse
ensure the safe installation and operation of the mast climber
2011 Part 2 foreman /
when attached to the building supplier
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 48
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.