             Mast Climber                             The electrical power supply required to safely operate the            WH&S Reg            Site manager /
              electrical failure                                                                                              2011
                                                       mast climber is to be reviewed, provided and installed by a            Chapter 5,6
                                                                                                                                                  supplier / licensed
                                                       licensed electrician                                                                      electrician
             Falling Objects                                                                                                 Vic OHS Reg
                                                   5                                                                          Part 3.5 and        Site manager /
                                                       Mast Climber contractor/supplier to provide a Safety Plan and
                                                                                                                              5.1
                                                       Safe Work Methods on the safe set up, erection, servicing and                              foreman /
                                                       dismantling of the Mast Climber                                                            contractor
                                                   5   Mast Climber supplier to provide an engineer’s drawing to                                  Site manager /
                                                       verify the layout of the platform to be used, spacing, fixing                              foreman /
                                                       method and type of mast ties to be used in the securing of the                             Supplier/engineer
                                                       mast climber to the structure
                                                   5   A commissioning report must be provided to the site                                        Site manager /
                                                       manager/foreman by a competent person certifying that the                                  foreman / installer /
                                                       mast climber has been installed as per the engineer’s drawings                             Subcontractor/
                                                       and is safe for common use before the mast climber may be                                  supplier
                                                       used onsite.
                                                   5   Operators of the mast climber must be trained in the safe                                  Site manager /
                                                       operation of the mast climber by a competent person                                        foreman / installer /
                                                       provided by the supplier of the mast climber – provide                                     Subcontractor/
                                                       records to the site manager/foreman                                                        supplier
                                                   5   All pre-start checklist and safe operational checks must to be                             Operator /Foreman/
                                                       carried out by the trained operator at the start of each day –                             HSO at Induction
                                                       records to be kept on site
                                                   5                                                                                              Site Manager /
                                                       All services and repairs carried out on the mast climber is to
                                                                                                                                                  foreman /
                                                       be carried out by a competent persons and all records
                                                                                                                                                  competent
                                                       recorded in the mast climber log book
                                                                                                                                                  person/supplier
                                                   5   Subcontractors using the mast climber are to provide a safe                                Site manager /
                                                       work method statement in the safe operation and work                                       subcontractor
                                                       activities to prevent falling objects when performing work on
                                                       the mast climber.


                                   C   4    E18   5/   As general access to the site (or specific site area) presents a      WH&S Reg       D3   Site Manager / HSO
☒   Noise    Exposure to
              excessive noise
                                                  6    significant noise exposure hazard, signage will be erected to          2011 Part
                                                                                                                              4.1            M9
                                                       identify this issue and require mandatory personal protective
             Exposure to low                                                                                                Managing
                                                       equipment (ear protection) to be worn.                                 noise and
              level noise
                                                   5   Noise will be kept to a minimum on site.                               preventing          All personnel
                                                                                                                              hearing loss
                                                   5   Safe Work Method Statements will include details of specific           at work 2011        Subcontractor / HSO
                                                       activities that create excessive noise levels, and noise control       QLD, NSW &
                                                       methods to be implemented while working on site.                       SA

                                           WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                                                                                    Page 49

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.