Whsmp · OPW16/0021

of 586

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (16.2 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 137, section 1. The text section number identifies this passage in the reader.

        5   Controls will be implemented to ensure the effective                Site Manager /
            management of exhaust emissions (i.e. plant operating above         Subcontractor
            trenches and excavations and in confined / enclosed areas).
        3   All machinery on site will be provided with guarding around         Subcontractor / HSO
            parts that move, pose a risk of entanglement, are excessively
            hot / cold, have the potential to eject parts or transmit power.
        5   Duties of employers are to carry out an assessment of the risks     Site Manager /
             associated with the hazards when operating plant. A Plant          Subcontractor
             Risk Assessment Pre-Start Checklist must be completed for
             plant & equipment to ensure that employers have assessed
             the fit for purpose to operate the plant on site and comply with
             duties of employers for the management and control of plant.
             The following plant types and inspection requirements are to
             be check against the Plant Risk Assessment Pre-start Checklist
             reference numbers for compliance;
             Tower Cranes -
             Mobile Cranes
             Mobile Concrete Boom Pump
             Satellite Concrete Boom Pump
             Earth moving equipment
             Scissor and Boom Lifts
             Hoist and Mast Climbers
             Piling Rig
             Mobile Concrete line pump
             Man & Material Hoist
             Mast Climber
             Forklift
             Other
            -
            -
            Where plant is found to be noncompliance the plan shall;
             Be removed off site
             Tagged out until the defective item/s has been fixed
        5   Servicing schedules will be placed on the Hutchinson Builders       Site Manager /
            Plant & Equipment Register prior to equipment being used on         Subcontractor
            site. This register shows the service/ maintenance duration
            and date of the last service for each item, for example;
            Plant to be serviced as per manufactures servicing
            requirements – as a guide;
                 1. Electric Tower Cranes - commissioning - monthly
                       inspections requirements then every 3 month
                       interval inspections requirements
WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                 Page 53

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.