3 Personnel will be excluded from the area between the area Site manager or
within 2m of any live end anchorage and between the live end foreman /
and the barricade. subcontractor
5 Barricades, flagging and signage will be erected. Site manager or
foreman /
subcontractor
B 5 E24 5 Hutchinson’s Tilt-Up Checklist will be actioned prior to the WH&S Reg Site Foreman /
Pre-cast and Collapse of pre-cast
☐ Tilt up concrete units
lifting of Tilt-Up panels. Both parties will sign off on each issue
2011 Part 6
QLD Tilt-up
Subcontracotr
listed in the relevant column.
Construction and Precast
Objects falling 5 Safety plan / work method statement obtained from COP 2003 Subcontractor / HSO
subcontractor undertaking pre-cast placement or tilt up VIC OHS or Foreman
Insufficient crane/
construction on site is to address the following issues: Regulation
lifting equipment
Provisions of shop drawings and engineer certification Part 5.1
considerations AS 3850-
Methods of controlling vehicle access around the pre-cast 2003
work area Methods of controlling vehicle access around the
pre-cast work area
Any hazards associated with overhead power lines, trenches
and recent excavations
Casting layout and panel storage positions
Crane size and placement requirements
Erection sequence and bracing layout
Orientation and identification of panels
5 The supervising engineer is to inspect and assess the following Site Manager /
procedures: Engineer
Initial casting of tilt up or pre-cast panels for compliance
with shop drawings
Initial lifting of tilt up or pre-cast panels and
Subsequent casting and lifting of panels at random intervals
5 Documentation verifying the following is to be available on Site Manager /
site: Subcontractor
The concrete specification of concrete supplied on site for
use in panels
The minimum final concrete strength (i.e. 28 day strength)
of concrete delivered to the site
The minimum concrete strength to be achieved prior to
lifting of panels (information for the inserts should be
available that specifies the minimum concrete strength
required for the insert.)
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 57
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.