How many days are to elapse between casting and lifting of
panels
Results of a sampling program that demonstrates the
concrete is of an appropriate strength
The casting dates for each panel and earliest date when the
panel can be lifted (each panel should be numbered and
written records made)
5 After winds of 7m/s (25km/h) or more have been experienced Subcontractor / HSO
at the job site, the tilt up contractor must check the tightness or Foreman
of the bolts that secure the wall and footplates to the
concrete.
4 A minimum of two braces will be secured to each panel unless Subcontractor / HSO
specified by the engineer and indicated on the erection or Foreman
drawings. Where only one brace is used there will be a
minimum of two fixings at each end.
4 No part of the bracing support system will be removed until Subcontractor / HSO
the panel has been permanently anchored and inspected by or Foreman
the tilt up contractor.
5 Rigging work associated with tilt-up and pre-cast units will be HSO at Induction
under the control of a worker certified as an intermediate or
advanced rigger at all times.
3 An exclusion zone will be established so that only those HSO or Foreman /
persons directly involved with the erection of panels are in the Subcontractor
area while lifting is taking place. The exclusion zone will be set
up so that it includes an area where persons cannot be struck
either by:
The crane falling over,
The panel being lifted falling over, or
Another structural element failing and falling to the ground
as a result of being struck by the crane or the panel being
lifted.
5 Hutchinson’s Pre-cast Checklist to be actioned prior to the Site Foreman /
lifting of Pre-cast panels. Both parties must sign off on each Subcontracotr
issue listed in the relevant column.
D 3 M9 5 Where work is undertaken that requires the closure of WH&S Reg D2 Site Manager
☒ Public
Protection
Falling Objects
footpaths and roads, specific risk assessments, employment of 2011 Part 6
L5
VIC OHS Act
Plant and traffic controllers or the preparation of traffic management
2004 s23
equipment plans will be undertaken in accordance with statutory
requirements and to suit the environment and method of
work, which is required.
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.