Original PDF page 143, section 1. The text section number identifies this passage in the reader.

 Traffic and                         5   Where the drivers of vehicles, trucks and plant turn up            Site Manager
  pedestrian control                      unannounced to site and are required to reverse into the site
                                          across public footpaths an walkways the following is to be
 Slips, trips and falls
                                          implemented;
                                          ☐Erect a sign at the entry gates “Directing drivers to contact
                                               the site manager/foreman before entering site – provide
                                               phone numbers.
                                      4   ☐Email suppliers and subcontractors to advise them of the
                                               health and safety protocol to be followed for plant &
                                               vehicle movements onto the site.
                                          ☐Where there are members of the public using the footpath
                                               or walkways provide a spotter or mechanical aids to
                                               control their movements during the reversing process.
                                          ☐The reversing vehicle, plant and trucks from the street to be
                                               controlled as per the traffic management plan for the
                                               project
                                 1. 1     For QLD: Around the perimeter of the site based on the angle       Site Manager
                                          made between a) the horizontal and b) an imaginary line
                                          drawn between the closest point where the public have
                                          access, to the highest point on the building/structure where
                                          work is to be done:
                                 2.       The fencing will be:
                                           (< 15 o)       ☐ barricade or hoarding at least 900mm high
                                          (15o – 30o)     ☐ A hoarding at least 1800mm high.
                                              o
                                          (30 – 75 )o
                                                          ☐ a hoarding at least 1800mm high that is fully
                                                             sheeted with timber, plywood, metal or
                                                             sturdy synthetic sheets
                                          (75o or more) ☐ a hoarding at least 1800mm high that is fully
                                                             sheeted with timber, plywood, metal or
                                                             sturdy synthetic sheets, AND one of the
                                                             following;
                                                              a gantry (or overhead protective
                                                                 structure), (incorporating the hoarding),
                                                                 or
                                                              the adjoining area is closed to prevent
                                                                 objects falling on or otherwise hitting
                                                                 members of the public in that area; or
                                                              A catch platform with vertical sheeting
                                                                 or perimeter containment sheeting is
                                                                 installed.



                           WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                                            Page 59

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.