3.4 For NSW: Where work is carried out at a height exceeding 4m Site Manager
above the lowest ground level of the adjoining public place the
following will be implemented:
a hoarding at least 1800mm high that is fully sheeted with
timber, plywood, metal or sturdy synthetic sheets, AND
one of the following;
a gantry (or overhead protective structure),
(incorporating the hoarding), or
the adjoining area is closed to prevent objects falling
on or otherwise hitting members of the public in that
area; or
A catch platform with vertical sheeting or perimeter
containment sheeting is installed.
Unless the ration of the horizontal distance to the vertical
height between the nearest boundary of the public place and
the where the work is carried out exceeds 2, in which case the
requirements as per for QLD (above) will be implemented.
5 Written approval will be obtained from the relevant authority Site Manager
to close adjoining areas when excluding members of the
public. Any controls imposed by the authority will be fully
implemented and monitored during the project.
5 “Construction Site – No Unauthorised Entry” signs will be used HSO / Foreman
to clearly identify areas on and around the perimeter of sites
as being a place of work.
5 During installation, extension or reduction of catch platforms Subcontractor/
or screening, appropriate measures (i.e. such as closing the Hutchinson Builders
adjoining area) will be taken to ensure that a falling
component cannot injure a member of the public in the
adjoining area.
5 Public areas will be kept clear of any debris, trip or slip hazards HSO / Foreman
and protected from any projectiles, dust etc. that may be
released as a product of work undertaken.
4 Brick cages that fully enclose the load will be used when Subcontractor
craning bricks and other suitable materials around the project.
4 Hoardings erected on site will: Subcontractor / HSO
a) be able to withstand a horizontal force of-
i) 500 N/m2 applied over 1m2 at the top of the hoarding
midway between any two posts without deforming
permanently; and
ii) 950 N applied over 1500mm2 at any point on the
hoarding without fully penetrating the hoarding;
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 60
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.