Whsmp · OPW16/0021

of 586

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (16.2 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 151, section 1. The text section number identifies this passage in the reader.

                                                       5   Signs and devices will be erected and displayed before work             Vic Road            Subcontractor /
                                                           commences. Signs and devices will be removed from a work                 Managemen
                                                                                                                                    t Act 2004          Foreman / HSO
                                                           site only after all work is completed and as soon as practicable
                                                           after completion of the work.
                                                       5   Signs and devices will not direct a motorist to disobey the                                  Subcontractor /
                                                           traffic regulations, unless an authorised person / traffic                                   Foreman / HSO
                                                           controller is present to direct traffic.
                                                       5   Each traffic management area will be inspected and recorded                                  Subcontractor /
                                                           at the start of each day.                                                                    Foreman / HSO
                                                       5   Each traffic management area will be inspected throughout,                                   Subcontractor /
                                                           and at the completion of, each day.                                                          Foreman / HSO
                                                           The Certificate of Competency in Traffic Control for each traffic                            HSO at induction
                                                           controller is to be sighted and copied (where there is a facility)
                                                           at induction.
                                                       5   A detailed diary/log will be maintained for all actions taken by                             Subcontractor /
                                                           a traffic controller on site which includes details of signage and                           Foreman / HSO
                                                           traffic control setup on a daily basis and time of control set up,
                                                           modifications or controls removal, hours of operation and
                                                           surface condition of the road.
                                                       6   Additional reflective helmet, vest, leggings and light baton will                            Subcontractor /
                                                           be worn and used for night works.                                                            Foreman / HSO
                                                       4   Night lighting will be provided for night works to ensure traffic
                                                           controllers are visible to oncoming traffic.
                                                       2   Consideration will be given to conducting work out of peak                                   Site Manager /
                                                           times.                                                                                       Foreman
                                                       5   In the case of any incident, the type, size, location and                                    Site Manager / HSO
                                                           arrangement of signs and devices, weather conditions and
                                                           conditions of travel path will be recorded and photographed.
                                                       5   Where vehicles, plant or trucks are to be directed to reverse                                Site Manager / HSO
                                                           from the roadway into the construction site across public
                                                           footpaths or walkways – ensure that members of the public
                                                           using the footpaths and walkways are controlled as per the
                                                           Project Risk Assessment titled “Public Protection” and SWMS
                                                           titled “SWMS 23 - Traffic Control”


                                       C   4    E18    5   All tasks involving welding or hot work will have an approved           WH&S Act      C3    Subcontractor / Site
☒   Welding and
    Hot Work
                   Contact with hot
                    surfaces
                                                           SWMS in place that takes into account at least the following             2011 Part 2
                                                                                                                                                  H13   Manager
                                                           issues / hazards (as appropriate):
                                                                - contact with hot surfaces

                                               WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                                                                                          Page 67

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.