Anchorage brackets attached to steel roofing
material
Anchorage bracket to framed steel structure
The above anchorage systems are installed by person
that has completed a Work Safely at Heights course
4 Appropriate edge protection (consisting of the necessary Site Manager or
handrails, mid-rails, toe-boards/kickboards and/or infill that foreman /
are adequate to provide support against workers and objects Subcontractor
from falling from an edge or platform) will be erected and
maintained during the work activities on site.
6 Wrist straps or rope lanyards will be used to secure tools to Site Manager or
persons or work platforms in an attempt to prevent objects foreman /
falling. Subcontractor
The following controls will be implemented to protect foreman /
workers, the public and property below the work area: Subcontractor
4 scaffolding with safety mesh,
4 safety/catch nets,
4 the erection of a gantry,
4 Restricted / barricaded access of the ground or area
below the work being undertaken at height.
4 a gantry (or overhead protective structure),
5 (incorporating the hoarding)
the adjoining area is closed to prevent objects falling
4 on or otherwise hitting members of the public in that
area, or
4 A catch platform with vertical sheeting or perimeter
containment sheeting is installed.
Any penetration that exposes workers to the risk of
being struck / injured by falling objects will be
covered in an adequate manner to prevent the
movement of the applied cover
5 All workers required to use personal fall protection equipment foreman /
are to be competent in the inspection, use and maintenance Subcontractor
of such equipment – completed a Work at height training
course pursuant of AS 1891.4 (2.2.10 User Competency)
5 Inspection Requirements for fall arrest equipment Site Foreman/
Application subcontractor
- Personal equipment including harnesses, lanyard Competent person
assemblies, connectors and fall-arrest devises
including common use devices.
Activity
- Inspection by operator before and after each use.
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 71
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.