                                                                                       Hutchinson Builders – ABN:52 009 778 330

                                      WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                     Version: 9.2



      3.4       HB Provided Plant
In relation to this project, the following items of plant shall be provided by HB for general use by employees
and subcontractors on site:

☒       All temporary fences erected on the proposed line of the construction site are to be maintained on a
        daily basis by site team members – refer to [Public Protection Controls within Section 4 for additional
        details].

☒       Signage:

          Signs will be fixed at entrances to the site, on perimeter hoardings in a number of easy to see
           locations.
          Signs fixed to fence – ensure stability of the fence panel
          Signs will include, but not be limited to, the following:
                   “Construction Site – Do Not Enter Authorized Personnel Only” signs,
                   Mandatory Safety Helmet and Safety Footwear Signs,
                   “HB” Construction Site General Signs, and
                   Directional and descriptive signs indicating the location of the site office, toilets, first aid
                    provisions, traffic management etc. as required.
☒       Construction workplace amenities to be provided in accordance with PP:04 – Construction
        Amenities for the :

          Site office’s, meeting and checked by the site team members during all on-site inspections.
☒       Generator

          Generators will be tested by a licenced electrician on a 3 monthly basis.
          Generators to be run through an earth leakage.
          Generators powering Hoist and crane are to be used exclusively for the specified plant.
☐       Compressor

          Safety clips are to be affixed and maintained for hose connections
          Equipment to be maintained and serviced as per manufacturer’s specifications.
☐       Hoist

          Hoists will be maintained and serviced in accordance with the maintenance & service schedule.
          Licenced Hoist Operators will be responsible for the operation of the Hoist at all times the
           hoist is operational.
☒       Crane (Tower or mobile)

          Crane equipment will be erected in accordance with the engineer approved Site Lift Plan;
          Safe work zones will be created and maintained for the duration of the time the crane is on
           site, with specified exclusion zones;
          Licenced Crane Operators and Dogmen will be responsible for the operation of the crane and
           hooking of all loads at all times; and


                                                                                                                   Page 21 of 58

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.