Hutchinson Builders – ABN:52 009 778 330
WHSMP:01 – Work Health & Safety Management Plan
Version: 9.2
A monthly servicing schedule will be maintained unless the manufactures specifications
stipulate otherwise.
☒ Forklift
Maintenance inspection to be completed in accordance with the service and maintenance
schedule.
Daily prestart checks will be completed prior to the use of the plant.
Only suitably licenced persons are to operate the plant.
☒ Scissor / boom
Scissor / Boom will be maintained in accordance with the maintenance and service schedule.
Daily prestart checks will be completed prior to the use of the plant.
Only suitably licenced persons are to operate the plant.
☒ Scaffolding
Scaffold is to be erected as per approved scaffold plan.
Scaffold plant registration number is to be displayed at the main site access point or on the
font entry fence.
The scaffold handover certificate must be received prior to the scaffold being used by any
trades. Handover certificates are also to be obtained following any alterations to the scaffold.
Only competent licenced persons to erect / dismantle / alter scaffold.
Scaffold to be reinspected at regular intervals not exceeding 1 month.
Page 22 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.