                                                                            SWMS:18 – A Pre Cast Panel Erection – N/A
Safe Work Methods
                                                                                                                                                        Responsible
                                                                                  H                      Controls / Work Methods                                        Residual Risk
                                                                                                                                                        Person/s for
          Job Steps                    Potential Hazards           L    C    R    O              1. Eliminate 2. Substitute 3. Isolate 4. Engineer       Monitor &       L    C     R
                                                                                  C                               5. Admin 6. PPE                          Review
                                                                   C    4     E    5     Workers are to be aware of mobile plant movements.           Hutchinson       D     4    H
                                  Contact with powered
                                                                             18                                                                        Builders Site               14
                                  mobile plant                                           Operators must be aware of other workers when
                                                                                                                                                       Foreman
                                                                                          reversing, slewing or moving forward.
                                                                                   5
                                                                   C    4     E    5     Deadmen are to be constructed and installed as per the       Hutchinson       D     4    H
                                  Deadmen constructed /
                                                                             18           engineers design drawings and specifications inclusive       Builders Site               14
                                  installed incorrectly
                                                                                          of wind loadings and potential effects on the panels.        Foreman
                                                                                         Deadmen are to be cast using low strength concrete
                                                                                                                                                       Design
                                                                                          (20-25MPa) and left for a period of time to ensure that
                                                                                   5                                                                   Engineer
                                                                                          any cast in or drill in type anchors do not pull out.
                                                                                         Documentation is to be obtained from an engineer that
                                                                                          verifies that each deadmen has been constructed in
                                                                                          accordance with the drawings and the concrete has
                                                                                   5      obtained its minimum strength prior to installation of
                                                                                          the braces and / or installation of drill in type anchors.
                                                                   C    5     E    4     Cast-in inserts (CBW 20/65 coils and ferrel bolts) are to    Design            E    5    H
                                  Drill in type anchor not fixed
                                                                             22           be used to fix tilt-up braces. Drill-in type anchors are     Engineer                    15
                                  correctly
                                                                                          only to be used where the use of cast-in inserts is not
                                                                                          practicable.                                                 Hutchinson
                                                                                   4     Bottom brace anchor will be a reid anchor bracing            Builders Site
                                                                                          anchor 2.2 tonne 20mm/120mm. A drill of 20mm                 Foreman
                                                                                          diameter will be used for the bottom brace anchor
                                                                                          holes.
                                                                                         Deformation controlled anchors, drop – in type anchors,
                                                                                   1
                                                                                          low load slip controlled anchors (wedge anchors) and
                                                                                          self-drilling anchors are not be used for anchoring
                                                                                          braces.
                                                                                   4     Where drill-in type anchors are used they may be –
                                                                                          undercut type anchors that do not rely on friction to


584 Milton Road TOOWONG QLD 4066                             SWMS Developed by:   Jamie Gilbert                                                             VERSION 9 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                          Position:            National Health & Safety Co-ordinator                                                        Page 21
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.