SWMS:18 – A Pre Cast Panel Erection – N/A
Safe Work Methods
Responsible
H Controls / Work Methods Residual Risk
Person/s for
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Monitor & L C R
C 5. Admin 6. PPE Review
function, expansion anchors of a high-load slip, torque
controlled type, or coil bolts.
5 Coil bolts must be installed in accordance with
manufacturer’s specifications and that the permissible
load on the anchor is not to exceed 0.65 of the first slip
load.
5
Drill-in type anchors are to be installed according to the
engineer drawings and manufacturer specifications.
5 The panel concrete is to be allowed to reach a minimum
strength of between 20-25MPa before the braces can
be attached.
5 Where the anchor limits the permissible capacity of the
brace: an anchor with a higher capacity, attaching more
braces to the panel, or more than one expansion anchor
5 on the brace foot is to be used as determined by the
engineer.
The anchor torque setting is to be as per the
documented manufacturer’s specifications.
Delivery and unloading of Pre- C 4 E 5 When unloading panels the semi trailer is to be located Hutchinson D 4 H
Truck roll over, instability
Cast Panels on site 18 on firm, level ground. Builders Site 14
Foreman
The side slope must be minimal and not exceed 2
5
degrees.
Truck Driver
The wheels are to be chocked in addition to applying the
4 park brake.
5 The trailer is to be unloaded in a progressive manner
that ensures any tilt of the trailer is kept to a minimum.
Note: It may be necessary to lower the front support legs
of the semitrailer prior to removing the panels (this will
help to reduce movement of the trailer).
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 9 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 22
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.