                                                                           SWMS:18 – A Pre Cast Panel Erection – N/A
Safe Work Methods
                                                                                                                                                             Responsible
                                                                                 H                      Controls / Work Methods                                              Residual Risk
                                                                                                                                                             Person/s for
          Job Steps                    Potential Hazards           L   C    R    O              1. Eliminate 2. Substitute 3. Isolate 4. Engineer             Monitor &       L    C     R
                                                                                 C                               5. Admin 6. PPE                               Review
                                                                                  5     Where there is a risk of plant (crane boom or loads etc)           Crane
                                                                                         coming near an exclusion zone, appropriate controls are            Operator
                                                                                         to be in place before the lift occurs as per the relevant
                                                                                         State / Territory electrical safety legislation an electrical
                                                                                         supplier requirements eg; authorised spotter, tiger tails
                                                                                         or limit switches on cranes
                                                                   C   4     E    5     Assist crane crew                                                  Foreman          D     4    H
                                  Panel crew assisting Dogman
                                  / rigger being struck by panel
                                                                            18    1     Panel crew members are not allowed to enter the crash                                          14
                                                                                         zone during panel placement.                                       Crane and
                                                                                        STAND CLEAR until the panel is near final position, and            rigging crew
                                                                                  1      directed by rigger to assist
                                                                                                                                                            Panel Crew
                                                                                        Daily Pre-starts to be undertaken prior to the lifts
                                                                                  5
                                                                                         between crane crew and panel crew to discuss safe
                                                                                         lifting controls
                                                                   C   5     E    5     The crane support is to be maintained until all braces             Hutchinson        E    5    H
                                  Panel collapse (from
                                                                            22           have been installed and effectively secured to the panel           Builders Site               15
                                  incorrectly installed braces,
                                                                                         and footings (hoist rope and lifting gear not to become            Foreman
                                  mobile plant movement, lack
                                                                                         slack until this is achieved).
                                  of crane support)
                                                                                  4     Braces are to be installed to prevent the collapse of the          Plant
                                                                                         panel during erection as per engineer’s drawings and               Operators
                                                                                         these braces:
                                                                                           -    Be designed by an engineer and to provide a factor of
                                                                                                safety of 2 against failure.
                                                                                           -    Be permanently marked with the manufacturer’s name,
                                                                                                model type, working load limit and minimum extensions;
                                                                                           -    Have engineering certification and be designed to have
                                                                                                adequate strength and stiffness allowing for wind
                                                                                                loadings.
                                                                                           -    Be inspected prior to use to check there is no damage and
                                                                                                to verify the braces are complete and functional;


584 Milton Road TOOWONG QLD 4066                            SWMS Developed by:   Jamie Gilbert                                                                   VERSION 9 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                         Position:            National Health & Safety Co-ordinator                                                              Page 25
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.