SWMS:18 – A Pre Cast Panel Erection – N/A
Safe Work Methods
Responsible
H Controls / Work Methods Residual Risk
Person/s for
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Monitor & L C R
C 5. Admin 6. PPE Review
5 Where there is a risk of plant (crane boom or loads etc) Crane
coming near an exclusion zone, appropriate controls are Operator
to be in place before the lift occurs as per the relevant
State / Territory electrical safety legislation an electrical
supplier requirements eg; authorised spotter, tiger tails
or limit switches on cranes
C 4 E 5 Assist crane crew Foreman D 4 H
Panel crew assisting Dogman
/ rigger being struck by panel
18 1 Panel crew members are not allowed to enter the crash 14
zone during panel placement. Crane and
STAND CLEAR until the panel is near final position, and rigging crew
1 directed by rigger to assist
Panel Crew
Daily Pre-starts to be undertaken prior to the lifts
5
between crane crew and panel crew to discuss safe
lifting controls
C 5 E 5 The crane support is to be maintained until all braces Hutchinson E 5 H
Panel collapse (from
22 have been installed and effectively secured to the panel Builders Site 15
incorrectly installed braces,
and footings (hoist rope and lifting gear not to become Foreman
mobile plant movement, lack
slack until this is achieved).
of crane support)
4 Braces are to be installed to prevent the collapse of the Plant
panel during erection as per engineer’s drawings and Operators
these braces:
- Be designed by an engineer and to provide a factor of
safety of 2 against failure.
- Be permanently marked with the manufacturer’s name,
model type, working load limit and minimum extensions;
- Have engineering certification and be designed to have
adequate strength and stiffness allowing for wind
loadings.
- Be inspected prior to use to check there is no damage and
to verify the braces are complete and functional;
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 9 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 25
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.