SWMS: 21 – Swing Stage Suspended Scaffolds - N/A
Risk Matrix
Perform a risk assessment for each hazard identified by:
(i) Determining the consequences (refer Table 1);
(ii) Determining the probability of the event occurring (refer Table 2);
(iii) Apply the values obtained from Tables 1 & 2 to the Qualitative Risk Matrix (Table 3) to obtain the resultant Risk Score and Level.
Table 1 – Consequence
Table 2 - Likelihood
Level Descriptor Example detail description $$$ Example
Low Financial Loss Level Descriptor Description Frequency
1 Insignificant No Injuries
<$500
First aid treatment, on- Medium Financial
The event is expected to occur in most More than once per
2 Minor site release immediately &/or Loss A Almost Certain
circumstances year
contained $500 - $5,000
Medical treatment
High Financial
required, on-site The event will probably occur in most
3 Moderate &/or Loss B Likely At least in once 5 years
release contained with circumstances
$5,000 - $25,000
outside assistance
Extensive injuries, loss Major Financial At least once in 10
C Possible The event might occur at some time
Major of production capability, Loss years
4 &/or
off-site release with no $25,000 –
detrimental effects $200,000 At least once in 30
D Unlikely The event could occur at some time
years
Death, toxic release off- Huge Financial
5 Catastrophic site with detrimental &/or Loss The event may occur only in exceptional Less than once in 30
effect >$200,000 E Rare
circumstances years
Table 3 – Risk Level / Priority
Legend
CONSEQUENCES E: extreme risk; immediate reaction required (18-25)
LIKELIHOOD
Insignificant Minor Moderate Major Catastrophic H: high risk; senior management attention needed (10-17)
1 2 3 4 5 M: moderate risk; management responsibility must be
A (almost specified (6-9)
H 11 H 16 E 20 E 23 E 25
certain)
B (likely) M 7 H 12 H 17 E 21 E 24
L: low risk; manage by routine procedures (1-5)
C (possible) L 4 M 8 H 13 E 18 E 22
D (unlikely) L 2 L 5 M 9 H 14 E 19
E (rare) L 1 L 3 M 6 H 10 H 15
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 7 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 53
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.