SWMS:24 – Working with Explosive Power Tools
Safe Work Methods
H Controls / Work Methods Responsible Residual
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Person/s for Risk
C 5. Admin 6. PPE Monitor & Review L C R
death, serious bodily Records of inspections made to be documented on
injury or property Form A.
damage. Trained personal to install associated materials.
Placement of concrete to form Expose workers to C 4 E 5 Take care in screeding concrete to safe your backs Worker D 3 M
panel incorrect manual 18 refer SWMS:04. Foreman 9
handling movements Take care when reversing trucks near workers and
causing bodily injury. others, so not to place them at risk, refer SWMS
Expose workers and No.16
others when reversing Ensure that concrete is placed, vibrated and
concrete truck causing trowelled by experienced personal.
serious bodily injury. Record panel pour details on Form A.
Stripping of Formwork Expose workers to trips C 3 H 5 De-nail and carefully stack stripped formwork Worker D 2 L5
and spills from 13 panels. Foreman
incorrectly stacked Maintain clear access around the panel area after
formwork causing bodily stripping has occurred.
injury. Place disused materials in bins provided.
Digging and pouring concrete Expose workers to being B 5 E 5 Workers to be aware of plant and truck Employer D 4 H
pier and slab Deadmen struck by plant 24 movements. Site Foreman 14
Bore pier deadmen movements causing Workers to be eye contact with operator when Worker
death or serious bodily 5 working close by.
injury. Install as per engineer’s bracing layout DWG‘s and
Expose workers to 5 deadmen design layout DWG’s.
deadmen and Do not leave bore piers unattended, barricade off
connection failure 3 area until concrete is placed.
during brace sequence
causing death, serious
bodily injury or property
damage.
Slab type deadmen Expose workers to slab B 5 E 5 Install as per engineer’s bracing layout DWG’s. Worker D 4 H
and drill in fixing failure 24 Manufacturer requirements complied to for Foreman 14
during brace sequence securing drill in type anchors.
causing death serious
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 6 – May 2014
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 89
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.