Original PDF page 377, section 1. The text section number identifies this passage in the reader.

                                                                            SWMS:24 – Working with Explosive Power Tools
Safe Work Methods
                                                                                          H                   Controls / Work Methods                        Responsible            Residual
            Job Steps                     Potential Hazards             L    C    R       O           1. Eliminate 2. Substitute 3. Isolate 4. Engineer      Person/s for             Risk
                                                                                          C                            5. Admin 6. PPE                     Monitor & Review        L C R
                                          death, serious bodily                                    Records of inspections made to be documented on
                                          injury     or     property                                Form A.
                                          damage.                                                  Trained personal to install associated materials.
Placement of concrete to form            Expose      workers      to   C    4     E      5        Take care in screeding concrete to safe your backs    Worker                   D    3       M
panel                                     incorrect          manual               18                refer SWMS:04.                                        Foreman                               9
                                          handling      movements                                  Take care when reversing trucks near workers and
                                          causing bodily injury.                                    others, so not to place them at risk, refer SWMS
                                         Expose workers and                                        No.16
                                          others when reversing                                    Ensure that concrete is placed, vibrated and
                                          concrete truck causing                                    trowelled by experienced personal.
                                          serious bodily injury.                                   Record panel pour details on Form A.
Stripping of Formwork                    Expose workers to trips       C    3    H       5        De-nail and carefully stack stripped formwork         Worker                   D    2       L5
                                          and       spills      from              13                panels.                                               Foreman
                                          incorrectly        stacked                               Maintain clear access around the panel area after
                                          formwork causing bodily                                   stripping has occurred.
                                          injury.                                                  Place disused materials in bins provided.
Digging and pouring concrete             Expose workers to being       B    5     E      5        Workers to be aware of plant and truck                Employer                 D    4   H
pier and slab Deadmen                     struck       by       plant             24                movements.                                            Site Foreman                      14
 Bore pier deadmen                       movements          causing                               Workers to be eye contact with operator when          Worker
                                          death or serious bodily                         5         working close by.
                                          injury.                                                  Install as per engineer’s bracing layout DWG‘s and
                                         Expose      workers      to                     5         deadmen design layout DWG’s.
                                          deadmen                and                               Do not leave bore piers unattended, barricade off
                                          connection          failure                     3         area until concrete is placed.
                                          during brace sequence
                                          causing death, serious
                                          bodily injury or property
                                          damage.
   Slab type deadmen                    Expose workers to slab        B    5     E      5        Install as per engineer’s bracing layout DWG’s.       Worker                   D    4   H
                                          and drill in fixing failure             24               Manufacturer requirements complied to for             Foreman                           14
                                          during brace sequence                                     securing drill in type anchors.
                                          causing death serious
584 Milton Road TOOWONG QLD 4066                             SWMS Developed by:        Jamie Gilbert                                                                     VERSION 6 – May 2014
P: (07) 3335 5000 F: (07) 3335 5005                          Position:                 National Health & Safety Co-ordinator                                                          Page 89
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.