SWMS:26 – Demolition of Structures - N/A
Safe Work Methods
H Controls / Work Methods Responsible Residual
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Person/s for Risk
C 5. Admin 6. PPE Monitor & Review L C R
Remove glass panels, windows Expose workers to B 4 E 5 Assess the size of the glass and frame to be removed Employer D 3 M
and aluminium framing to all shattering glass when 2 and gain assistance if required from another worker Site Foreman 9
levels removing panes from 1 to secure the glass as the rubbers are removed. Exper/Worker
sections causing cuts and 4 Using glass suction lifting aids and gauntlet gloves
lacerations. remove the glass and place it in the area provided.
4 Using hand tools remove aluminium sections and
place in the area provided.
4 If required to work at height set up a stable work
platform (mobile scaffold or trestle).
1 Do not work at the edge of the floor or building where
you are exposed to a fall from heights.
1 Do not work off an extension ladder.
Remove plaster, timber, metal Expose workers to; B 4 E 5 Use the correct hand tools and electrical equipment Competent Person D 3 M
ceilings and walls at all levels o Cuts and lacerations 2 to remove the selected fixtures from the installed 9
o Strain and pulled 1 position.
muscles 6 Use adequate P.P.E. to carry out the task.
Remove allied service pipes, o Head injuries 5 Use correct lifting methods to lift fixtures and place in
wiring, ducts and conduits at all o Eye injuries the storage area.
levels 5 Store materials in the area provided.
4 If required to work at height set up a stable work
platform (mobile scaffold or trestle)
1 Do not work at the edge of the floor or building where
you are exposed to a fall from heights
1 Do not work off an extension ladder.
Workers exposed to B 4 E 5 Where practicable place materials into a lift box and Competent person C 4 E
Remove reusable materials from strained and pulled 2 lower to the ground using a crane. 1
all levels muscles caused by 1 4 Where practicable use existing lift or install a man and 8
continuous carrying and materials hoist to lower to the ground.
lifting. 5 Walk the materials down stairwells to a limit of 3
levels per person.
Remove generated rubbish and Workers exposed to falls B 4 E 4 Provide purposed built chutes to direct rubbish and Competent Person D 3 M
rubble from all levels when dumping rubbish 2 rumble to ground floor from levels above. 9
from heights. 1 o Chutes attached to the building or scaffold
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 7 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 99
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.