                                                                            SWMS:26 – Demolition of Structures - N/A
Safe Work Methods
                                                                                        H                    Controls / Work Methods                          Responsible           Residual
             Job Steps                     Potential Hazards            L   C   R       O            1. Eliminate 2. Substitute 3. Isolate 4. Engineer        Person/s for            Risk
                                                                                        C                             5. Admin 6. PPE                       Monitor & Review    L      C    R
                                          Other workers exposed                                  o Opening in floor to act as the chute
                                           to falling objects from                     4         All chute areas are to have edge protection and safe
                                           above working on the                                   dump access.
                                           site.                                       6         Workers are to wear adequate P.P.E.
                                          Workers and others                                    Bottom of chute area, must be barricaded off to
                                           exposed to dust and                                    prevent entry by others.
                                           noise during dumping                        5         Regularly water rubbish piles to contain dust
                                           methods
   Remove roof sheets        facade      Expose workers to falls      A   5   E      4         Provide a safe access and exit to the roof area via       Person(s) using     C      4    E
    sheeting and capping                   from heights accessing               2                 scaffold stairs, scissor lift, boom lift or safe ladder   Scaffold                        1
                                           the roof and removing                5                 access.                                                                                   8
                                           the sheets causing death                    4         When removing sheets workers are to be protected
                                           or serious bodily injury.                              by;
                                                                                                  o Fall restrain rope system working back along the
                                                                                                       roof sheets
                                                                                                  o Scaffold erected as edge protection
                                                                                                  o Scissor lift or boom lift
                                                                                       5          o Edge protection with safety wire under sheets
                                                                                                 Removed sheets are to lower to the ground by crane,
                                                                                                  scissor lift or passed down to the ground in a
                                                                                                  controlled manner then removed from site
   Remove      structural      roof                                    A   5   E      5           . Truss roofs are to be disconnected working in         Competent person    C     4     E
    members;                              Expose workers to falls              2                      the confines of a scissor, boom lift or mobile.                                      1
       -   Truss roofs                     from heights removing                5                  Steel columns, beams, rafters and purling are to                                        8
       -   Steel purlins and rafters       the     structural    roof                                  be dismantled by rigger / dogman as required.
       -   Steel beams                     members causing death                                   All removed roof members are to be lower by
                                           or serious bodily injury.                                   crane or passed to the ground in a controlled
                                                                                                       manner then removed from site.
Removal of external walls                 Exposed workers to falls     B   5   E      5         Use the correct hand tools, electrical equipment or air   Competent           C     3     H
adjoining public buildings                 from heights removing                2                 tools to remove the selected materials from the           person                          1
                                           materials from wall                  4                 installed position.                                                                       3
                                           causing serious bodily                      6         Use adequate P.P.E. to carry out the task.
                                           injury                                      4
584 Milton Road TOOWONG QLD 4066                           SWMS Developed by:       Jamie Gilbert                                                              VERSION 7 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                        Position:                National Health & Safety Co-ordinator                                                       Page 100
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.