                                                                                                     Construct & Erect Tilt-Up Concrete Panels Safety Checklist
                                                                                                                                                         HB-HSEQ-F-062
                                                                                                                                                             Version: 4


Qualifications / Competencies: Experienced qualified tradesman, trained person, qualified engineer licensed rigger and crane operator
                                                                                                                         Signed By:
                                                                                                                           Checked -
Item No.              TASK DESCRIPTION                                   ACCEPTED CRITERIA                                             BUILDER   COMP/PERSON
                                                                                                                              √
    1       Foundations and footings are          •   Installed as per engineer design drawings
            structurally adequate.
    2       Casting beds installed.               •   Set in correct location to avoid over reaching of crane
                                                  •   Panel Lift sequence planned from each bed
    3       Documentation is provided on site.    •   Panel shop drawings and engineer’s letter certifying DWG’s to
                                                      AS 3850.
                                                  •   Bracing and deadmen design DWG’s and engineer’s letter
                                                      certifying DWG’s to AS 1170
                                                  •   Panel crew safety plan on site
                                                  •   Crane/rigging safety plan on site
    4       Panels cast in accordance with the    •   Release agent applied, panel layout checked and panel
            DWG’s and poured.                         numbered and dated
                                                  •   Concrete placed, vibrated and MPA checked
                                                  •   Record Panel info on – Form A – refer in SWMS
    5       Deadmen and anchors installed ready   •   Deadmen installed to engineer’s design and as per bracing layout
            for bracing.                              plan
                                                  •   Concrete to have reached 20-25mpa strength before fixing props
                                                  •   Drill in type anchors to meet manufacturer’s requirements for
                                                      the weight of the panel and concrete MPA.
    6       Lifting Panel into Position.          •   Crane and rigging gear to suite panel weight
                                                  •   Identify any overhead power lines
                                                  •   Ground conditions stable to suite crane movements
                                                  •   Lifting clutches compatible with panel inserts
                                                  •   Slings and clutches marked with ID plates
                                                  •   Certification of crane operator and rigger on site
                                                  •   Exclusion zone to protect the public and other workers in place
                                                  •   Workers involved understand their duties
                                                  •   Lift as per Panel records – Form A



                                                                                                                                                           Page 1 of 2

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.