HUTCHINSON BUILDERS | established 1912

Sea View Terrace Traffic Management Plan March 2016
Ref. MCU14/0084
Preamble

Hutchinson Builders has been engaged to construct a private residence on vacant land situated at 71
Seaview Tce. Sunshine Beach QLD.

A MCU approval has been granted with conditions that necessitate the lodgement of a Traffic and
Pedestrian Management Plan as part of the Operational Works submission.

The Operational Works application has been submitted on behalf of the owner by Martoo Consulting
and this plan forms part of that submission.

MCU Conditions

This submission seeks to address conditions 18-19 of the MCU14/0084 Decision Notice
A) Objectives

To observe the MCU conditions

1. To minimise the impact the movement of traffic to and from the worksite will have on the
premise occupants of Seaview Tce.

2. To protect the safety of occupants and pedestrians on the street and footpath of Seaview
Tce.

3. To ensure that access is maintained to the residences of Seaview Tce and to the worksite.

4. To reduce the incidence of compliant to the local government authority.

B) Constraints

1. Roadway width: Seaview Tce. between Macannaly Dve and the cul-de-sac, allows for
one street car parking on the western side of the street only. The distance between a
parked car and the edge of the asphalt seal is less than 3 metres, with the road reserve
sloping away from the roadway edge.

2. Other building works: Construction work is current in this section of the street. Delivery
trucks are at times unloaded from the street. This prevents passageway of vehicles in
and out of Seaview Tce. Similar renovation and new construction work can be expected
over the duration of the building programme.

3. The site is situated at the termination of a narrow access handle that does not provide
for the parking of workers vehicles. The site itself provides little opportunity for site
accommodation, storage of materials.

This plan recognises each of these constraints and submits the following in consideration.

(see over page}

es

MJ.Leeke Page 1

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.