Objects falling. 5 Cranes will be sited to minimise the need for other plant to the Workplace
Site Manager /
QLD COP 2013
Severe weather operate within the crane’s operating radius. Tower Crane Subcontractor
effecting lifting 5 QLD COP 2006
Cranes and other plant with counterweights will be sited so Managing the Site Manager /
activities. that counterweights cannot collide. risks of plant Subcontractor
in the
5 The tower crane’s climbing procedure will ensure that the Site Manager /
workplace
crane remains as far above any of the structure of plant as NSW COP Subcontractor
practicable. 2014
5 The following must be provided before a crane may be used Plant VIC COP
1995
Site Manager /
on site: Subcontractor
Safeguarding
- Current plant registration Of Plant And
- List of workers undertaking prescribed work. Machinery WA
- Full details of the erection procedure (if applicable) COP 2009
- Full details of the procedures for operation of the crane Managing The
Risk Of Plant
(including communication methods). In The
- Evidence that all crane attachments/lifting gear is to be Workplace
tested and tagged and in a serviceable condition for use TAS COP 2012
on site.
- Manuals for operation, servicing and maintenance are
available and kept on the crane.
- Full details of all inspections, repairs and maintenance are
to be supplied in a logbook.
- Full details of the procedure for dismantling of the crane
(if applicable) separate to those provided for the erection
of the crane.
5 The records of the pre-erection inspections and tests and Site Manager /
commissioning reports must be provided to Hutchinson Subcontractor
Builders prior to the use of a crane onsite.
5 Information to be provided to the crane operating Site Manager &/or
subcontractor prior to commencement of work on site HSO
includes:
- location and details of underground cavities
- location and details of underground services
- location and details of excavations
- locations of embankments and soft surfaces
- potential overheard structures / services
- necessary load/working requirements
- any information on ground bearing capacity that is
available to Hutchinson Builders
- foreseeable operating conditions to Hutchinson Builders
5 Hutchinson Builders will provide to the crane operator Site Manager &/or
documented information about the ground bearing pressure HSO
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.