Skip to the record
Trusted by locals. Built for Noosa.

Council archive · source document

Tod Consulting Stormwater Plans v2 · 132003.221172.A

Attached to the e-mail Change to DA - 132003.221172.A.msg.

of 22

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
The site is located on a beach dune. Although the geotechnical information provided by Global Testing Pty Ltd
(refer Attachment 2) did not provide an infiltration rate for the saturated hydraulic conductivity of the in-situ
sands, previous work in the area and empirical values for soils in this area indicate a saturated hydraulic
conductivity at the site were likely to be a minimum of k=2.56 x 10-3 m/s (9216 mm/hr). All calculations within
this document are based on this value. No information as to the depth to groundwater was available and it is
assumed that the base of infiltration trenches can be located at least 1.0 m above the seasonal high water table.

The methodology for the design of infiltration trenches is contained within “The WSUD Technical Design
Guidelines for South East Queensland” was adopted for this project. Chapter 7 of these Guidelines outlines two
alternate methodologies for the sizing of trenches being; the Hydrological Effectiveness Method and the Design
Storm Method. Calculation by both methods was undertaken for comparison.

The Hydrological Effectiveness Method aims to size an infiltration trench such that a specified proportion of the
mean annual runoff volume will infiltrate into the soil profile. The guidelines provide a series of design curves
based on an idealised tank/trench layout for estimation of trench size. Based on the geotechnical information
provided and an assumed trench of 0.9 m deep and 0.8m wide (porosity = 0.95 being an Atlantis Flo-Tank). This
assumes a system that the double tank system and 2 cells wide. Figure 7-7 of the Guidelines indicates that a
trench with an area equal to 1.5% of the catchment area would achieve a hydrological effectiveness of 100%.
That is, an infiltration trench with an area of 1.5% of the catchment and 1 m deep would infiltrate 100% of the
mean annual runoff from the site.

The alternate method for infiltration tank sizing is the Design Storm Method. As determined above the design
objective is to capture and infiltrate up to a 1% AEP (1 in 100 year ARI design event) runoff volume. This method
sizes a required detention volume based on the following:

    -   the volume of runoff from the catchment during the design event;
    -   the saturated hydraulic conductivity of the in-situ soil/sand; and
    -   the dimensions of the proposed trench including the length, width and height of the trench.

The required detention volume is the difference between the volume of runoff from the catchment and the
volume that can be infiltrated during a rainfall event.

From the hydrologic model outlined above the volume of runoff from the proposed lots was calculated (using
the WBNM model output) for the 1% AEP event.

Table 3 shows the calculated infiltration requirements and the number Atlantis Flo-Tank (double) to cater for
these infiltration requirements. Detailed calculations are provided in Attachment 3.

Table 3: Required Infiltration – Atlantis Flo-Tank (Double – 2 cells wide)
                                      Volume Based on     Volume Based on
                                                                                 Required
  WBNM Sub-                             Hydrological        Design Event                           No of Atlantis
                       Area (ha)                                      3      Infiltration Area
  Catchment                             Effectiveness       Method (m )                2         Flo-Tank (Double)
                                                   3                                (m )
                                        Method (m )             (Vd)
  Site (excluding
 area draining to       0.0416              6.24                5.77               6.42                 25
       road)


                                                                                    m: 0439 119 890 t: +7 5414 7185
                                                                                    e: [email protected]
                                                                                    w: www.aquaintel.com.au

Used in these records

About this file

File size
6.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Tod Consulting Stormwater Plans v2.pdf · 6.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.