shown in Figure 1. The sub-catchment areas and fraction impervious values for the catchments are tabulated
below in Table 1.
Table 1: WBNM Sub-Catchment Areas and Fraction Impervious Values
Developed Scenario
WBNM Sub-Catchment Area (ha)
Impervious (%)
Roof (to street) 0.009 100%
Roof 0.013 100%
Drive to Rear 0.0036 100%
North East Grass 0.007 50%
North_side 0.0059 50%
South_side 0.0065 50%
Backyard 0.0056 10%
The WBNM model has been validated with comparison of peak flows derived using the Rational Method and a
reasonable agreement was achieved. The WBNM model adopts a catchment lag parameter of 1.6, which is
within the accepted range of values provided in the WBNM technical reference manual. The rainfall loss rates
adopted for this investigation are an initial and continuing loss of 0mm and 2.5mm/hr for pervious, and 0mm
and 0mm/hr for impervious.
Peak flows tabulated below in Table 2 represent the developed peak flow for each design storm event with the
critical duration varying from 5 to 15 minutes (5 minute for 100 year). Output summary provided in Attachment
1.
Table 2: Developed Scenario WBNM Peak Flows
2yr ARI 5yr ARI 10yr ARI 20yr ARI 50yr ARI 100yr ARI
Catchment 3 3 3 3 3 3
(m /s) (m /s) (m /s) (m /s) (m /s) (m /s)
To Street 0.004 0.005 0.005 0.006 0.007 0.008
To Rear 0.019 0.023 0.026 0.029 0.033 0.037
Infiltration Trench Sizing
Discussion with Noosa Council (pers. Comm. Mark Lewis, 31 May 2016) indicated that the development would
need to demonstrate that runoff to the rear of the property for all but the most extreme rainfall events would
be infiltrated on-site so as not to cause scour or slope instability on adjacent properties. As such it was
determined that an infiltration trench or trenches would need to be sized to cater for the infiltration of all
design events up to and including the 1% AEP (1 in 100 year ARI design event).
m: 0439 119 890 t: +7 5414 7185
e: [email protected]
w: www.aquaintel.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Tod Consulting Stormwater Plans v2.pdfRelated documentApplication case desk ↗
About this file
- File size
- 6.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.