Figure 1: Stormwater Catchment Plan



STORMWATER QUANTITY

Calculation of Flows

The objective of this study is to calculate the stormwater flows generated from the proposed development and
to size infiltration tanks / trenches to cater for the likely flows that cannot be discharged to the Street.

Hydrologic modelling has been carried out using the WBNM software for the 2, 5, 10, 20, 50 and 100 year ARI
storm events. Calculation of flows has been completed for the proposed developed case. As it is the objective of
the development to ensure runoff is infiltrated prior to leaving site to the rear there was no need to investigate
non-worsening of peak flows and thus no need for comparison with existing conditions.

An assessment was completed on the current site layout defined in the hydraulic services plans by Ian Bradford
Plumbing Consultants (20/06/2017). These plans have highlighted that 90m2 of the site can be directed to the
street. To be conservative in the infiltration sizing it has been assumed that the remainder of the site will be
directed to one of the two proposed infiltration locations.

The contributing catchment of 505 m2 has been represented using six sub-catchments being the Front Yard,
Driveway, North East Grass, Roof (both roof areas combined) and Backyard areas. The catchment layout is

                                                                                     m: 0439 119 890 t: +7 5414 7185
                                                                                     e: [email protected]
                                                                                     w: www.aquaintel.com.au

Used in these records

About this file

File size
6.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Tod Consulting Stormwater Plans v2.pdf · 6.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.