STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125

of 492

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 276, section 1. The text section number identifies this passage in the reader.

                                                                                                                                                                                          Residual
                                                      Rating
                                                      Initial
                                                                                                                     Proposed Controls




                                                       Risk




                                                                                                                                                                                            Risk
           Activity                    Hazard                                                                                                                                                              Responsible Person




                                                                HOC
                                                                                         (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)

                              Worker injured or    EXTREME      5     Where a worker is required to work alone or in an isolated situation, a risk assessment shall be                     M         Site Management
                              incapacitated                           completed assessing the following risks:                                                                                       HSE Advisor with BSBWHS414 OHS
                                                                                                                                                                                                     Cert 4
                                                                       -   length of time the person needs to complete the job.
                                                                       -   evacuation procedure
                                                                       -   time of day
                                                                       -   communication procedure during the work
                                                                       -   communication procedure during an emergency
                                                                       -   location of the work
                                                                       -   nature of the work
                                                                       -   skills and capability of the worker


     7.7 Portable Power Tools
Planning                      Activity planning    HIGH         5     All tasks involving powered tools will have an approved SWMS or SOP in place which considers the job                  L        Site Management
                              and hazard                              steps and task hazards. following hazards:                                                                                     Contract Partner
                              identification                           Only competent persons are permitted to operate portable electrical tools on-site

                              Exposure to          HIGH         6          Appropriate PPE will be used whilst undertaking tasks involving portable power tools.                            L        Site Management
                              excessive noise                                                                                                                                                        Contract Partner

Use of electrical equipment   Injury               HIGH         5          All tools will be used in accordance with the manufacturer’s specifications.                                     L        Site Management
                                                                                                                                                                                                     Contract Partner
                              Injury               HIGH         1          Compressed air should never be directed toward the body as this can lead to serious injury or death.             L        Site Management
                                                                                                                                                                                                     Contract Partner

     7.8              Explosive Power Tools
Use of electrical equipment   Workers not          HIGH         5          Explosive power tools will be always stored in a securely locked container when not in use and will             M         Site Management
                              suitably licenced or                         not be removed from container unless for use, repair or maintenance or left unattended unless                             Contract Partner
                              trained for the                              precautions are taken to ensure that it will not come into the possession of an unauthorised person.
                              activity

                              Excessive noise      HIGH         3          When using explosive power tools barricading will be used where the risk of other personnel                     M         Site Management
                              levels                                       entering the area is considered “HIGH.” This barricading is to isolate the work area where the                            Contract Partner
                              Flying particles /                           explosive power tool is being used and shall be erected in all directions.
                              materials
                              Injury




                                                                                                                                                         Project Hazard/Risk Assessment / Page 34 of 160

Used in these records

About this file

File size
58.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdf · 58.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.