STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125
Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Original PDF page 321, section 1. The text section number identifies this passage in the reader.
Residual
Proposed Controls
Rating
Initial
HOC
Risk
Risk
Activity Risks Responsible Person
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Manual handling EXTREME 5 Any remotely / automatically operated machinery will be appropriately signed and barricaded to ensure persons are not Site Management
put at risk.
Contract Partner
Unsafe plant use EXTREME 5 Persons will not travel on / be lifted by / moved by / any item of mobile plant unless it has been specifically designed for Site Management
on site that purpose.
Contract Partner
Workers not
suitably licenced
or trained for the
activity
Plant failure EXTREME 5 Plant which lifts or moves loads will be marked with its SWL and will be used within this limit. Site Management
Contract Partner
Plant failure EXTREME 3 All plant is to be assessed for its capacity, based on OEM (Original Equipment Manufacturer) manuals, to undertake the Project Manager
duty of the intended task. Considerations for terrain, climate, ground bearing capacities and conditions, batters and cross
falls, gradients etc. are to be considered in this assessment. Site Manager
Struck by plant EXTREME 5 Personnel involved with the operation of mobile plant on site and those personnel in the vicinity of mobile plant Site Management
movements. operations on site will wear high visibility vests or clothing.
Contract Partner
Plant failure EXTREME 5 All Contract Partner’s will provide a register for all equipment to be used on site. This register must show the date of the Site Management
last service for each item and when the next service is due for each item.
Contract Partner
Contact with EXTREME 5 Underground services, overhead power lines, unstable ground, and other excavations in the vicinity will be identified and Site Management
overhead or details given to the Contract Partner.
underground Contract Partner
services
Plant failure EXTREME 5 A plant and equipment register will be maintained on site for all plant used by Woollam personnel and plant provided for Site Management
general use on site. This register will detail records of any tests, maintenance, inspections, commissioning, or alteration
of the plant. Contract Partner
Plant failure EXTREME 5 Woollam will ensure plant is inspected and effectively maintained throughout the course of the project. Site Management
Project Hazard/Risk Assessment / Page 79 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 58.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.