STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125

of 492

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 336, section 1. The text section number identifies this passage in the reader.

                                                                                                                                                                                      Residual
                                                                                                                                                                                                   Responsible




                           Rating
                           Initial
                                                                                                     Proposed Controls




                                     HOC
                            Risk




                                                                                                                                                                                        Risk
Activity        Risks
                                                                        (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)                                              Person




           Ground          HIGH      3     Ground compaction test to confirm ground conditions meet the requirements of the approved scaffold design.                                             Site Manager
           conditions

           Working near   EXTREME    4     Risk assessment to be conducted prior to erecting scaffold within 4m of low voltage overhead powerlines.                                              Site Management
           energised                                                                                                                                                                             Contract Partner
                                           Asset owner advice to be obtained in advance of scaffold erection.
           overhead
           powerlines                      In accordance with asset owner’s advice, trained electrical spotters to be engaged for erection and dismantle where scaffold
                                           installation is within 4m of low voltage overhead powerlines or risk assessment requires a spotter.
                                           Ply hoarding to be installed in accordance with asset owner’s advice when is installed within 4m of overhead low voltage power.
                                           (Safe Work Australia)




                                                                                                                                    Project Hazard/Risk Assessment / Page 94 of 160

Used in these records

About this file

File size
58.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdf · 58.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.