RFI - Attachment 3 - Stormwater Management Plan
Original PDF page 20, section 1. The text section number identifies this passage in the reader.
- External Reuse demands
o 75% of pervious landscaping per dwelling will be irrigated with an annual application of 548mm
o Each dwelling has an indicative 90m² pervious area in proximity
o Annual irrigation of 36.99kL per dwelling
A typical rainwater tank node configuration is shown below in Figure 4.3 – Typical Tank node configuration
Figure 4.3 – Typical Tank node configuration
4.1.1.2. Pit Inserts
All grated inlet pits within the driveway are to be fitted with Ecosol Litter baskets with 1500µm filter Bags. These
have been certified by the manufacturer as having the pollutant removal efficiencies shown in Figure 4.4 - Ecosol
Litter Basket Pollutant Removal Efficiencies. The inserts are modelled using generic treatment nodes, with a high
flow bypass of 106L/s per pit and concentration-based capture efficiency set in accordance with manufacturers
guidelines. Refer to Appendix D Ecosol Litter Basket Technical Specification for further details on the devices.
Project number 21020 Page 20 of 36
File RECOR Concept Stormwater Management Report - 21020.docx, 2022-09-05
Revision 0
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads Qld 4567 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (RFI - Attachment 3 - Stormwater Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.