Delegated Report - Code - Planning OPW26 0033 (As Published)

of 27
                      b.      certification from a suitably qualified person (RPEQ and/or CPESC) must be submitted
                              to Council certifying that the erosion and sediment controls on site have been installed
                              in accordance with the Plan and IECA’s Best Practice Erosion and Sediment Control.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               5.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      civil engineering works;
                      b.      arboreal (tree) works;
                      c.      fauna management works;
                      d.      landscape works;
                      e.      rehabilitation works;
                      f.      erosion and sediment control works; and
                      g.      other relevant parties.
               6.     Prior to requesting a prestart meeting:
                      a.      Tree protection fencing must be installed under the supervision of the qualified person*.
                              (Refer to Retention of Existing Trees conditions).
                      b.      Pre-clearance surveys and habitat assessment required by the approved Fauna
                              Management Plan and conditions of this Decision Notice, must be undertaken (Refer
                              to Fauna Management conditions).
               7.     Submit a copy of the approved plans that are issued “For Construction” and duly signed by
                      the consultant Registered Professional Engineer of Queensland (RPEQ). Plans must be
                      submitted and approved by Council prior to the pre-start meeting.
               8.     Submit certificates demonstrating currency of public liability insurance and works insurance
                      covering the works. Certificates must be submitted to Council prior to the pre-start meeting.
               9.     Submit a condition report documenting any existing defects in the road reserve or
                      infrastructure, including photographs of the site frontage. The report must be submitted to
                      Council prior to the pre-start meeting.
               10.    Submit a Construction Management Plan to Council prior to the pre-start meeting. The
                      Construction Management Plan must specifically address the following:
                      a.      traffic management during all aspects of the construct phase including:
                              i.       a Traffic Management Plan in accordance with Manual of Uniform Traffic Control
                                       Devices (MUTCD) detailing all temporary signage and traffic control measures
                                       prior to construction;
                              ii.      maintenance of safe vehicle and pedestrian access across the frontage of the
                                       site both during daily construction and after daily construction has ceased;
                              iii.     proposed fencing to the site during the construction phase of the development;
                              iv.      adequate parking arrangements for construction workers and deliveries; and
                              v.       no queuing of trucks is permitted on residential streets;
                      b.      maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures;
                      c.      works programme identifying key components of the works and their respective
                              durations;

                                                                                                        Page 12 of 27

Document Set ID: 25027781
Version: 3, Version Date: 13/08/2026

Log in to download the original (Delegated Report - Code - Planning OPW26 0033 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.