TRAFFIC MANAGEMENT
The first operation will be the installation of the micro piles and
excavation of footings. During this stage the builder shall engage
the services of a traffic management company to ensure there is no
interference to the general traffic using Park Road. Traffic
controllers will be required to be present to divert vehicles during
the installation of micro piles and excavation of footings.
Traffic controllers will divert all vehicle deliveries and departures to the
site on Park Road. The timing of deliveries shall be such that they do
not coincide with peak usage times in Park Road.
Refer to Traffic Guidance Scheme prepared by Evolution Traffic
Control for details of proposed traffic management.
The builder warrants that using the procedures nominated above the
elevated terrace can be safely constructed with minimal impact on the
environment including the protected trees.
Original Construction management plan produced by
STEFAN PRYSTUPA, B.Eng (Civil); M.I.E.Aust; C.P.Eng; RPEQ Sep 2017
JOB NO. 17543
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Compiled Approved Plans OPW17/0561.01.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.