Minor Change Existing Approval 132004 5744 13 [As Published] · 132004.5744.13

of 17

Text shows just the words. Original shows the document exactly as it was published.

               49.    All pathways and pram ramps (internal and external) shall be designed and constructed to
                      ensure pedestrian safety using non-slip materials and to produce an evenly graded surface
                      finish.
               50.    All redundant vehicular crossings to the site shall be removed and replaced by kerb &
                      channel, footpath paving and landscaping such as trees and grasses in accordance with
                      Council’s Standard specifications prior to commencement of the use permitted by this permit.
               Pathway Contributions
               51.    A pathway contribution of $49,774 towards external major pathways, in accordance with
                      Planning Scheme Policy PSP41 Coastal Major Pathway Contributions, shall be paid to the
                      Council prior to obtaining a Development Permit for Operational Works. This amount will be
                      subject to variations in the Consumer Price Index, All Groups Brisbane from June 2005 until
                      the date of payment.
               Undergrounding Power
               52.    The power supply both external and internal shall be underground. This work shall be at no
                      cost to Council.
               Stormwater Drainage
               53.    All stormwater drainage from the site shall be collected on site and discharged generally in
                      accordance with Plan - Drainage Design 0379 SK 05B dated October 2004 prepared by Greg
                      Gibbs Architects, so there is no net increase in stormwater runoff from the site up to a Q100
                      event. Plans of the drainage design shall be prepared by a Registered Professional Civil
                      Engineer and submitted to Council prior to obtaining a Development Permit for Operational
                      Works.
               54.    Roof runoff from any new dwelling unit or apartment shall be directed to a rainwater storage
                      system or tank (minimum storage 1400 litres per dwelling unit (villa) and 1000 litres per
                      service or non-serviced apartment) that is plumbed to service the toilets in the new dwelling
                      and landscaping areas. The design of the rainwater storage system shall be to the
                      satisfaction of the Manager Plumbing Services.
               55.    Overflows from rainwater tanks may be discharged into the gravel drains proposed.
               56.    An approved maintenance plan for the treatment system shall be incorporated in the
                      Management Scheme for the development and a copy of this shall be provided for Council’s
                      records prior to commencement of the approved Use.
               57.    All site stormwater drainage shall be by means of a gravity system.
               Sewer and Water
               58.    The site shall be connected to Council’s existing sewerage reticulation systems and be
                      constructed in accordance with Council’s standards and requirements at no cost to Council.
               59.    All internal water and sewerage reticulation to be designed and constructed in accordance
                      with Noosa Shire Council Engineering Design Guidelines (PSP6).
               60.    A concept plan detailing proposed internal water and sewer reticulation network is to be
                      submitted for approval prior to preparation of Operational Works Drawings.
               61.    An application for Operational Works, Water Supply and Sewerage detailing proposed
                      internal water supply and sewerage reticulation works is to be lodged with Council in respect
                      of the proposed development.
               62.    After completion of internal water and sewerage reticulation, all works shall be considered
                      as “private sewers and water mains” and responsibility for operation and maintenance shall
                      be the property owners.
               63.    The water connection to the water reticulation system shall extend to the property boundary
                      and be metered.




                                                                                                     Page 8 of 17
Document Set ID: 23615315
Version: 3, Version Date: 05/03/2025

Used in these records

About this file

File size
212 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 132004 5744 13 [As Published].pdf · 212 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.