Information Request OPW25 0042 [As Published] · OPW25/0042
Provide a table identifying each property fronting Serenity Close for the section of
Serenity Close which grades to the sag and provide an explanation of how the direction
of drainage for each property has been determined (in particular, where it is assumed to
not fully drain to Serenity Close).
2. Clarify what design blockage values have been adopted for the stormwater inlets in the
design case in the overland flow assessment.
3. Clarify what climate change assumptions have bene adopted in the overland flow
assessment.
It is suggested that SPP2-4.5 and a planning horizon of 2100 be adopted consistent with
the current methodology of ARR.
4. It is noted that 1% AEP (2100) immunity for the staff facilities building is achieved by the
use of a levee (block wall).
It would be preferable if the levee was only used to achieve freeboard rather than 1%
AEP (2100) immunity.
5. Provide further contours or sections in the location of RIP 3B and RIP 5 to demonstrate
that surface levels or an overland flow path (which may be informal) will allow and
surcharge flows from these devices to flow to a lawful point of discharge without
impacting any of the development buildings or facilities.
6. It is noted that a gabion rock wall is specified as the method of retaining along the edge
of the overland flow swale in places. Given the ability of water to seep into this type of
retaining (large voids), it is unclear if this method of retaining is suitable for the edge of
a drainage channel and if a more suitable method is available that provides better long-
term performance of the channel and adjoining areas.
Issue – Overland Flow Channel
The design of the Overland Flow Channel includes roughness assumptions consistent with
mown grass or rock at a maximum batter of 1:2. Council has concerns with the ability to
provide long-term stabilisation for a grass or rock 1:2 batter.
Information Required
7. Provide additional detail demonstrating how long-term stabilisation will be provided to
the batters of the Overland Flow Channel. The additional detail must be prepared by a
suitably qualified person (RPEQ) and include treatment options consistent with the
current hydraulic design assumptions of the Overland Flow Channel (i.e., turf or rock).
Where long-term stabilisation of the proposed 1:2 turfed/rocked batter isn’t achievable,
provide a revised set of drawings amending the Overland Flow Channel to include a
reduced batter (i.e., a 1:3 vegetated batter).
Issue – Extent of Vegetation in Overland Flow Channel
The higher order development plans suggest that the trapezoidal channel will include
landscaping (beyond turf) in the Overland Flow Channel. This is Council’s preferred outcome.
However, the inclusion of vegetation within this channel is inconsistent with the current
hydraulic design assumptions and could lead to flow breaking out of the channel and cause
flooding.
Information Required
8. Confirm the Overland Flow Channel will be vegetated to achieve a natural channel
design and meet the required hydraulic design assumptions.
Page 2 of 3
Document Set ID: 23692869
Version: 3, Version Date: 16/04/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Information Request OPW25 0042 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 105 KB (small file)
- File type
No other editions are linked here.