Table 11-2: Location of Water Quality Monitoring at the Essence of Peregian Site

               Site                  Site No.                                       Description

  Wetland A2                              1         Monitor quality of stormwater entering wetland A2
  Wetland A2                              2         Replicate monitoring of stormwater quality entering
                                                    wetland A2
  Wetland B2                              3         Monitor quality of stormwater entering wetland B2
  Wetland B2                              4         Replicate monitoring of stormwater quality entering
                                                    wetland B2
  Wetland C2                              5         Monitor quality of stormwater entering wetland C2
  Wetland C2                              6         Replicate monitoring of stormwater quality entering
                                                    wetland C2
  Heath                                   7         Monitor quality of stormwater entering the receiving
                                                    waters
  Heath                                   8         Replicate monitoring of stormwater quality entering the
                                                    receiving waters
  Heath                                   9         Replicate monitoring of stormwater quality entering the
                                                    receiving waters
  Construction Site                      10         Monitor rainfall onto construction site
  Inflow onto                            11         Monitor quality of stormwater entering construction site
  construction site
  Inflow onto                            12         Monitor quality of stormwater entering construction site
  construction site
  Outflow from                           13         Monitor quality of stormwater exiting construction site
  construction site
  Outflow from                           14         Monitor quality of stormwater exiting construction site
  construction site

Locations are as per the sampling map, included as Appendix F.

Monitoring needs to commence during the construction phase, and continue during the
operational phase.

11.1       Water Quality Monitoring During Construction

          During construction, monthly monitoring for the parameters described in Table 11-1 is
          recommended from sites 7 to 9 (Table 11-2). Additionally, it is recommended that the
          suspended solids concentration of stormwater is measured at sites 10 to 14 during
          stormwater events, with collection of four (4) stormwater samples flowing onto the
          construction site, four (4) more stormwater samples flowing from the construction site
          into the terminal wetland, and a rain-gauge is installed on site to indicate the intensity of
          rainfall during a stormwater event (Table 11-2).

          Inflow and outflow water needs to be collected as paired samples within a short time
          frame, with each pair representing the same phase of stormwater activity. The volume
          of stormwater generated in the catchment can be calculated by the area of catchment
          and the intensity of rainfall during the event.    The proportionate change in the
          suspended solids loads in stormwater flowing over the construction site will provide a
          measure of the sediment being generated from the construction site.



©2012 Simmonds & Bristow Pty Ltd                         Contrast Constructions                           J-1005-310 - 13 January 2012
I.\CLIENTFILES\Contrast Constructions\1108-155c - Essence of Peregian SCEP Stage 1 Update\09_output Documents\1108-155C_SWMP
SCEMP_Scanlon Property Group V3.0 ta_120113.doc                                                                           Page 19 of 24

Used in these records

About this file

File size
26.7 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

PART Response to Information Request.pdf · 26.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.