Lake MacDonald Drive Cooroy - WMP
Workplace Management Plan
Lake MacDonald Drive, Cooroy
Emergency Drills
An emergency drill is carried out within 4 weeks of project commencement and as a minimum every 3 months
thereafter, or earlier when a risk assessment has identified a need to do so. Emergency drills are undertaken to
evaluate the effectiveness of the plan and personnel involved. Emergency drills are to be scenario based, each
drill considering a different situation.
Evidence that emergency drills have taken place is recorded on the Emergency Evacuation Drill Effectiveness
Form IMS-05-09. Where a deficiency in the plan has been identified, the plan is reviewed, updated and
corrective / preventative actions implemented. Corrective / preventative actions are to be noted on the drill
effectiveness form and dealt with, in accordance with section 20 subsection ‘Rectification Action Plan (corrective
action / preventive action) / System Improvement’ of this plan.
The Project and Emergency Management Teams are deemed competent and appropriately trained once
completing the training as detailed in Table 4 below.
Table 4 – Emergency Training Requirements
Organisation
Organisation
Provide First
HLTAID001
HLTAID003
Procedures
Emergency
Emergency
Emergency
Operate as
Fire Safety
Shadforth
Shadforth
Induction
Training
Training
Lead an
Provide
Control
Control
Project
Part of
Paper
Paper
CPR
Aid
Construction Manager ✓ ✓ ✓
Project Manager ✓ ✓ ✓
WHSE Advisor ✓ ✓ ✓
Foreman ✓ ✓ ✓
Emergency Warden ✓ ✓ ✓ ✓
Emergency Officer ✓ ✓ ✓ ✓
First Aid Officer ✓ ✓ ✓ ✓ ✓ ✓
Emergency & First Equipment
Workplace emergency and first aid equipment requirements are identified by a member of the Emergency
Management Team or a person who has undertaken the qualifications of an emergency officer or equal or who
has completed the training as per Table 3. Emergency and first aid equipment is inspected, and maintenance
requirements assessed as part of Shadforth auditing and inspection processes, conducted by the compliance
team documented on project compliance audit IMS-05-76.
Emergency equipment will be identified by the completion of Project Emergency and First Aid Requirements
Risk Assessment Form IMS-05-32.
Emergency equipment that is identified will be added to the site’s calibration register e.g. air horns, UHF
handsets or base stations, fire extinguishers, first aid kits, snake bite kits.
15. INCIDENT MANAGEMENT
Shadforth are committed to reducing the cost in pain and suffering and loss of earnings of all workers,
contractors and visitors, and disruptions to work or damage to the environment. Efficient management of all
workplace incidents is a fundamental objective of the business. To this end, Shadforth have implemented an
Incident Management Procedure IMS-02-09 which is followed in the event of an incident. This procedure is
displayed in the site’s office.
Incidents are classified in line with the consequences stated in Shadforth risk matrix. Incident severity
classifications are as follows;
IMS-04-01_P – Reviewed – September 2020 Document Uncontrolled When Printed Page 28 of 60