SUPERSEDED - Decision Notice - DBW23 0056 & RAP23 0010 [As Published]
Damage to Services and Assets
20. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
REFERRAL AGENCY RESPONSE – RAP23/0010
The proposed development requires referral to Council for building work under Table 3 for the
variation to the building setbacks and proposed rooftop terrace.
You are advised that:
1. Council requires that any development approval for building work is subject to the conditions
stated in the development approval for DBW23/0056
Currency Period for Referral Agency Response
2. This Concurrence Agency response is no longer valid if the use has not commenced within
4 years of the date of this notice, unless otherwise extended in writing by Council.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Building and Construction Industry (Portable Long Service Leave) Levy
1. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Co-ordination of Operational Works Assessment
2. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
3. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Traffic management during construction;
b. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
c. provision for safe vehicle and pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased.
Page 5 of 8
Document Set ID: 22631865
Version: 3, Version Date: 23/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original