Town Planning Report and Appendices - Cooroibah
Attached to the e-mail Development Permit – 23 Jirrima Crescent, Cooroibah MCU16/0099.
The original of this document is very large (14.9 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Performance outcomes Acceptable outcomes Response Comment
AO31.4 After completion of the in-stream works, all areas It is not anticipated that the works will impact on any areas
of the bed and banks of the waterway that are outside of outside of the predicted footprint of the works. However
the approved permanent footprint of the works, and which should this occur, these areas will be returned to their
have been disturbed as a result of the construction or original profile and stabilised to promote regeneration of
raising of the waterway barrier works, are returned to their natural fish habitats.
original profile and stabilised to promote regeneration of
natural fish habitats.
And
AO31.5 By the completion of works, the profiles of the The proposed works will not significant impact on the profile
bed and banks are reinstated to natural stream profiles of the bed and banks or to the natural stream profile and
and stability. stability.
And
AO31.6 The waterway bed will be retained with natural The proposed works relate to the replacement of the
substrate, or reconstructed with substrate comparable to existing culvert. The works will not alter the waterway bed or
the natural substrate size and consistency. impact on the existing low flow channel of the waterway.
And
AO31.7 Vegetation and cover will be rapidly re- N/A Vegetation disturbance and removal associated with the
established so that the native plant community at the site works is to be minimised. All other vegetation on site is to be
can recover or be enhanced (for example, by using native retained, and re-establishment is not considered necessary
species). in this instance.
And
AO31.8 Fish habitats, including fisheries resource values, The monitoring of the success of fish habitat regeneration
will be able to naturally regenerate to pre-works can be a condition of the development approval.
conditions.
Editor’s note: Monitoring of the success of fish habitat
regeneration, within and adjacent to the work site, will be a
development permit condition.
Additional requirements for development within a strategic environmental area
PO32 Sediment and other polluting AO32.1 During construction: N/A The site is not within a strategic environmental area.
material must be captured during (1) environmental safety measures such as silt curtains
construction and operation of a waterway are used to capture sediments,
barrier.
(2) materials that are pollutants (such as debris,
chemicals, or construction material) are not stored in
the stream bed, unless they are to be used
immediately.
And
AO32.2 After construction the stream bed and banks are N/A Refer to Response AO32.1.
State development assessment provisions Module 5 — Fisheries resources 5.2 Constructing or raising waterway barrier works in fish habitats state code
22 July 2016 V1.9 Page 22 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.