Performance outcomes Acceptable outcomes Response Comment
protected to prevent erosion or slumping, by ensuring:
(1) the waterway bed is lined with the original top soil
retained during the construction
(2) materials that are pollutants (such as debris,
chemicals, or construction material) are removed
from the location and appropriately treated and
disposed of as waste outside the strategic
environmental area – for example to a managed
landfill
(3) temporary barriers are removed after use and the
natural materials either returned to their original
location in the strategic environmental area, or if not
taken from the strategic environmental area,
appropriately treated and disposed of as waste
outside the strategic environmental area – for
example to a managed landfill.
PO33 The works do not impede fish AO33.1 Works (except temporary works required for less N/A Refer to Response AO32.1.
passage particularly during critical than 20 business days) that are not drowned out regularly
periods that are important for breeding, must contain a fish way, the design of which is approved
feeding, nursery and recruitment of by the Department of Agriculture and Fisheries.
indigenous fish species. And
AO33.2 Any fish way must be operational at all times N/A Refer to Response AO32.1.
except where natural flows would have prevented fish
passage.
And
AO33.3 In the case of drought, any fish trapped in the N/A Refer to Response AO32.1.
impoundment must be rescued.
And
AO33.4 Vegetation and cover is retained or replaced to N/A Refer to Response AO32.1.
pre-work levels and conditions.
And
AO33.5 All works are constructed during periods when N/A Refer to Response AO32.1.
fish passage is least affected.
PO34 Development avoids or minimises AO34.1 Development demonstrates best practice N/A Refer to Response AO32.1.
any adverse impacts on environmental environmental management to meet relevant
values and water quality objectives for environmental values and water quality objectives of the
receiving waters (surface and Environmental Protection (Water) Policy.
groundwater) on site or leaving a site Or
State development assessment provisions Module 5 — Fisheries resources 5.2 Constructing or raising waterway barrier works in fish habitats state code
22 July 2016 V1.9 Page 23 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.