Vegetation to be
removed
Figure 12 - Existing culvert to be replaced to allow for safe access to proposed
compound area
The facility and all ancillary components will be constructed over the one title. A
copy of title is provided in Appendix B. Plans indicating the details of the
proposal form part of the documentation of this application.
The site access is considered to be appropriate given the nbn™ facility will not
be a significant generator of traffic.
During the construction phase, a truck will be used to deliver the equipment and
a crane will be utilised to lift most of the equipment into place. Any traffic
impacts associated with construction will be of a short-term duration and are not
anticipated to adversely impact on the surrounding road network. In the unlikely
event that road closure will be required, nbn will apply to the relevant
authorities for permission.
A total construction period of approximately ten weeks (including civil works and
network integration and equipment commissioning) is anticipated. Construction
activities will involve four basic stages:
• Stage 1 (Week 1) – Site preparation works, including field testing,
excavation and construction of foundations;
Page 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.