2017-06-06 - P&E Agenda Attachment 1 to Item 6 Draft Alignment Amendments Part 1 (Pages 1-907)

of 907

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (18.9 MB): the original may take a few minutes to open or download. The page text below is quick to read.

                                                                    column 1                                             column 2
            Including amendments to 3 July 2017




                                                                Specific Outcomes                       Probable solutions (if code assessablecode
The Noosa Plan



                                                                                                                       assessment)
                                                            stormwater drainage in a manner that       Manual of Urban Traffic Control Devices
                                                            allows the road to be trafficable in       (MUTCD) Part 9.
                                                            Q100 ARI local rainfall events; and
                                                  d)   verges and footpaths provide—
                                                       i. safe access for pedestrians and
                                                            cyclists clear of obstructions;
                                                       ii. an access area for vehicles onto
                                                            properties;
                                                       iii. a corridor allocated for services and
                                                            utilities; and
                                                       iv. additional amenity for minor roads.

                                                  O8 Stormwater drainage infrastructure is             S8.1 Stormwater drainage planning, design and
                                                  planned, designed and constructed to—                construction is in accordance with Section 4 of
                                                  a)   be accessible, cost effective and easily        PSP5 Engineering Design Standards – Roads,
                                                       maintainable;                                   Drainage and Earthworks;
                                                  b)   protect downstream capacity;                    AND
                                                  c)   protect downstream water quality;               S8.2 As Constructed data is submitted in
                                                  d)   maximise on-site stormwater retention and       accordance with Section 6 of PSP5 Engineering
                                                       retardation; and                                Design Standards – Roads, Drainage and
                                                  e)   convey run-off to stormwater drainage in a      Earthworks;
                                                       manner that allows roads to be trafficable      AND
                                                       in Q100 ARI local rainfall events.              S8.3 Stormwater drainage planning, design and
                                                                                                       construction is in accordance with the
                                                                                                       Queensland Urban Drainage Design Manual.
                                                  O9 Roads and stormwater drainage                     S9.1 Roads and stormwater drainage
                                                  infrastructure is constructed—                       infrastructure is constructed in accordance
                                                  a)    in accordance with appropriate                 with—
                                                        engineering standards; and                     a)    Sections 2, 3 and 4 of PSP5 Engineering
                                                  b)    to minimise adverse environmental                    Design Standards – Roads, Drainage and
                                                        impacts, including from run-off and                  Earthworks;
                                                        erosion.                                       b)    Queensland Design Code for Residential
                                                                                                             Streets;
                                                                                                       c)    AUSTROADS; or
                                                                                                       d)    A combination of the principles in these
                                                                                                             documents;
                                                                                                       AND
                                                                                                       S9.2 Erosion and sediment control measures
                                                                                                       are designed and implemented in accordance
                                                                                                       with the Institution of Engineers Australia
                                                                                                       (Queensland Division) Soil Erosion and
                                                                                                       Sediment Control - Guidelines for Queensland
                                                                                                       Construction Sites.
                                                  Environmental Protection
                                                  O10 Roads and stormwater drainage                    S10.1 Roads and stormwater drainage follow
                                                  infrastructure are located and aligned so as to—     the edge of existing disturbed areas, or
                                                  a) minimise disturbance to native vegetation         alternatively, these works are co-located within
                                                       and/or other habitat areas;                     a combined utility corridor;
                                                  b) protect and maintain wildlife corridor            AND
                                                       movements and the safety of native fauna;       S10.2 Roads avoid native vegetation and
                                                  c) minimise changes to the hydrological              provide for fauna underpasses and associated
                                                       regime, including drainage patterns, run-off    fencing where appropriate;
                                                       and water quality;                              AND
                                                  d) avoid crossing watercourses, drainage             S10.3 Road infrastructure within or adjacent to
                                                       lines and wetlands, but where such              native habitat incorporates fences which allow
                                                       crossings are unavoidable, disturbed areas      for protected wildlife movement and controls


                                                                                                     156
                                                                                     Transport, Roads and Drainage Code

Used in these records

About this file

File size
18.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2017-06-06 - P&E Agenda Attachment 1 to Item 6 Draft Alignment Amendments Part 1 (Pages 1-907)(PDF, 18MB).pdf · 18.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.