Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
4.7 Disciplinary procedures
Non-compliance with safety procedures, legislation and instructions may result in various sanctions or disciplinary procedures for
company personnel, subcontractors or workers.
Disciplinary procedures may include
   Removal from site after three warnings
   Instant removal from site for serious breaches
   Instant dismissal
   Referral to authorities
   Demotion
   Transfer to another work site or position
   Back-charges
   Withholding progress payments
   Cancellation of contract
   Other (provide details below)
Other (details)

When non-compliances are identified, the responsible party will be issued with
   A verbal warning       A site safety instruction (see Appendices)         Other (provide details below)
Other (details)



4.8 Scaffolding
The following rules apply in relation to scaffolding on this project.
Scaffolding is present on this work site                                                              Yes     No
        Workers must not erect, dismantle, move or alter scaffolding in any way unless the worker is licensed and has been
        engaged specifically to perform scaffolding work at the work site. This includes removing or relocating scaffold planks, hop-
        ups, ties, handrails, brick guards or any other scaffold component. Anyone found contravening this requirement will be
        immediately removed from site;
        Workers must not use any scaffolding or part of the scaffolding that is incomplete or otherwise deemed unsafe for use;
        Scaffolding must only be accessed from designated access points (e.g. stairs, ladders, hop-up brackets where provided for
        access purposes). Climbing up star points and over handrails is strictly prohibited; and
        Any scaffolding defects should be immediately reported to nominated site supervisor.


4.9 Electrical switchboards and equipment
The following rules apply in relation to electrical switchboards and equipment on this project.
        No double adaptors, light-duty leads or domestic grade power boards are permitted on site;
        No electrical equipment required to be tested and tagged will be used unless the equipment has current testing tags or
        records.
        Switchboard lids and doors must not be left open, particularly when the board is exposed to the weather or located where a
        water hose is in use; and
        Workers must ensure that extension leads are:
               Not joined together to exceed the maximum allowable lengths listed under Section 3.14.2 - Electrical Equipment;
               Not run between different levels on multi-storey buildings (excludes fire stairs and lift cores)
               Wrapped around the insulated tie bar below the switchboard enclosure and pass through the opening in the bottom
               of the enclosure before being plugged into a power outlet; and
               Protected from damage by vehicles, plant, heat or liquids.



4.10 Amenities
4.10.1 Meal areas
        Food must only be consumed in the crib rooms or designated lunch areas;
        Lunch scraps, wrappers, drink bottles and disposable containers and utensils must be discarded in the rubbish receptacles
        and not left on tables or chairs;

WHSMP-C 01/2018.8                                                 Initials                                            Page 31 of 39

                                                  ____                             ____
Log in to download the original file

Project Management Plan.pdf · 350 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.