Project Management Plan
Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.
High risk construction work is construction work that involves a person performing any of the following activities:
Work where there is a risk of a person falling more than two metres;
Work on a telecommunication tower;
Demolition of an element of a structure that is load-bearing or otherwise related to the physical integrity of the structure;
Disturbance of asbestos;
Structural alterations or repairs that require temporary support to prevent collapse;
Work in or near a confined space;
Work in or near a shaft or trench with an excavated depth greater than 1.5 metres;
Work in or near a tunnel;
Using explosives;
Work on or near pressurised gas distribution mains or piping;
Work on or near chemical, fuel or refrigerant lines;
Work on or near energised electrical installations or services;
Work in an area that may have a contaminated or flammable atmosphere;
Tilt-up or precast concrete construction;
Work in or adjacent to a road, railway, shipping lane or other traffic corridor that is in use by traffic other than pedestrians;
Work in an area at a workplace in which there is any movement of powered mobile plant;
Work in an area in which there are artificial extremes of temperature;
Work in or near water or other liquid that involves a risk of drowning;
Diving work.
2.3.2 Requirements and layout
Any subcontractor intending to perform an activity that is high risk construction work on site must supply the Principal Contractor
with an appropriate safe work method statement (SWMS) before the work starts.
The Principal Contractor will ensure SWMS’s are prepared for any of its employees who are required to undertake high risk
construction work, and that the employees are provided with relevant training and instruction.
The Principal Contractor also reserves the right to request SWMSs or other evidence of risk management from subcontractors for
the management of any risks associated with any work, even work not classified as high risk construction work.
The SWMS for the activity must be prepared by the subcontractor in consultation with the subcontractor’s workers and any other
subcontractor who may be affected by the subcontractor’s work, and must:
Identify the high risk construction activity;
State the hazards related to the high risk work and risks associated with these hazards;
Nominate how these risks will be controlled;
Include processes for monitoring and reviewing the control measures;
Be consistent with the Principal Contractor’s WHS Management Plan and take into account the risks posed by other
subcontractors, work processes, plant and equipment at the work site;
Be available on site to workers performing the work;
Be easily understood by workers involved in the work.
Subcontractors will be responsible for training their workers in their SWMSs and ensuring they comply with the requirements of the
same.
The subcontractor’s supervisor on site must ensure:
Work is stopped immediately if the SWMS is not being complied with;
The SWMS is reviewed regularly and amended where necessary in consultation with the subcontractors’ workers to ensure
risks are being adequately controlled.
The Principal Contractor will record the date of receipt for all SWMSs in a site register (see Supporting documents).
The Principal Contractor will also monitor compliance with subcontractors’ SWMSs and may request amendments from time to time
to ensure the requirements of the SWMSs are appropriate for the work site.
A SWMS template is available through eDocs.
Prior to completing this section, refer to Risk Management and SWMSs in Supporting documents.
2.4 Worker training, licensing and induction
WHSMP-C 01/2018.8 Initials Page 5 of 39
____ ____
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Project Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.