Part 8 of 37 Appendix 6 - Flood Study MCU12/0208
Very large file (93.6 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Noosa on Weyba
Flood Study
~,.,CardnO.
Keyser Creek Tributary Crossing (Hollett Road East)
A crossing of this small tributary will be required to provide access to Precincts A, B, C, D, E, F and G. The
road level is quite variable. It is proposed that this road have 50 year ARI flood immunity and be trafficable
during a PMF event.
Several culvert crossings are required. They consist of 1/2700 by 1200 RCBC (upstream IL = 4.00 mAHD,
downstream IL = 3.75 mAHD, length = 25m); 1/600 RCP (upstream IL = 4.00 mAHD, downstream IL = 3.60
mAHD, length 25m); and 1/525 RCP (upstream IL 4.70 mAHD, downstream IL 4.50 mAHD, length
= = = =
25m). At other points along the road, underdrainage will be required for local overland flows.
This crossing is located to the north of the Noosa Wildlife Refuge. To allow for the safe passage of koalas
and other animals, between the Refuge and the environmental protection land on the subject site, the
minimum culvert height has been set at 1200mm, with a width of 2700mm. The Department of Main Roads
Fauna Sensitive Road Design (2000) indicates that culverts of this height have been known to allow for
passage of small, medium and large mammals, semi-arboreal mammals (which includes koalas),
microchiropteran bats, reptiles, birds, amphibians and introduced predators.
7.3 Proposed Stormwater Treatment
Numerous water sensitive urban design (WSUD)measures are proposed to treat stormwater. These include
bio-retention gardens and tree-pits located within the road reserve, vegetated swales, bio-retention swales,
bio-retention basins, litter baskets and rainwater tanks. For further details refer to the Stormwater
Management Plan (Cardno,October 2012). The proposed treatment measures will be located outside of the
100 year ARI extent of inundation. The waterway corridor will not be utilised for stormwater treatment
purposes; stormwater will be treated to a sufficient level before it is discharged to this area.
Northbrook Corporation Pty Ltd Version 1 23 October 2012
Flood Study v1.doc Commercial in Confidence Page 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 8 of 37 Appendix 6 - Flood Study MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 93.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.