Noosa on Weyba
Flood Study
~,.,CardnO.
8 Developed Case Results
8.1 Peak Water levels
The developed case peak water levels are shown in Appendix F. The resultant impact on peak water levels
for the local and regional flood events are also shown in Figures 22 to 35.
J&K Hofmann Site
The 100 year ARI peak flood level (with climate change) around Precinct H is approximately 3.01 mAHD.
Therefore the minimum floor levels in this area are 3.51 mAHD.
The 100 year ARI peak flood level (with climate change) around the northern section of Precinct I is
approximately 3.48 mAHD. Therefore the minimum floor levels in this area are 3.98 mAHD. (refer above)
The remainder of Precinct I is well above the flood level of the tributary, even with the easement in place.
The 100 year ARI peak flood level (with climate change) around Precinct K is approximately 7.16 mAHD.
Therefore the minimum floor levels in this area are 7.66 mAHD.
The 100 year ARI peak flood level (with climate change) around Precinct L is a maximum of 5.40 mAHD.
Therefore the minimum floor levels in this area are 5.90 mAHD Precinct J is located well above the flood
level of the tributaries.
The 100 year ARI peak water level over Hollett Road West is variable but is approximately 7.40 mAHD at the
crest, with a maximum depth of 50mm. The PMF peak depth is approximately 270mm, which is considered
trafficable. The dV product across the road in a PMF event is approximately 0.20m2/s. The peak water levels
immediately upstream of this crossing have been increased in major flood events. However, the increase is
generally contained within the road reserve and does not extend a significant distance upstream.
The 100 year ARI peak water level across the proposed easement crossing is 4.36m AHD, resulting in a
flood depth of 60mm, and so it is trafficable in a 100 year ARI event. It also has 10 year ARI immunity. This
crossing does not have PMF trafficability. This crossing could potentially improve flood access for the
neighbouring Lake Entrance Boulevard area. The peak water levels upstream of the easement crossing are
increased. This increase is contained within the site.
The water levels downstream of the easement are decreased by approximately 6mm in the 100 year ARI
event and 10mm in the 20 year ARI event. This decrease extends up to Lake Entrance Boulevard. In the 2
and 1 year ARI events, there are some small areas of increase of approximately 6mm downstream of the
easement, near the confluence with Eenie Creek. These increases are contained within the waterway area.
It should be noted that additional attenuation provided by the proposed rainwater tanks and bio-retention
basins is likely to reduce this impact.
The filling of the three lots within Precinct I has not had a noticeable impact on peak flood levels in this area.
Northbrook Site
The 100 year ARI peak flood level (with climate change) around Precinct F and G are approximately 2.86
mAHD. Therefore the minimum floor levels in this area are 3.36 mAHD.
The 100 year ARI peak flood level (with climate change) within Lake Weyba is 2.72 mAHD. Therefore the
minimum floor level for lots adjacent to the lake (Precinct B) is 3.22 mAHD. The other precincts in this area
are well above the flood levels.
The Hollett Road East tributary crossing has a variable flood level upstream. The maximum depth of
flooding in the 100 year ARI event is approximately 80mm across the road. In the PMF event the maximum
flood depth is approximately 270mm, and the dV product across the road is 0.30m2/s. The peak flood levels
upstream of this crossing are increased, however this area is a designated nature refuge, and the increases
do not extend a significant distance.
The Hollett Road East crossing of Keyser Creek has 100 year ARI flood immunity. The PMF flood level is
controlled by the regional PMF event, and so the peak depth of flooding is approximately 230mm in this
Northbrook Corporation Pty Ltd Version 1 23 October 2012
Flood Study v1.doc Commercial in Confidence Page 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 8 of 37 Appendix 6 - Flood Study MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 93.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.