Noosa on Weyba
Flood Study
                                                                                      ~,.,CardnO.

8.4       Flood Storage

The flood storage within Lot 11 on RP893393 for the existing and developed cases is shown below in Table
8-1. Due to filling required for lots and road crossings, the amount of storage on site has been reduced. At
2.25 mAHD, which is approximately the existing case 100 year ARI peak water level, the flood storage on
site has been reduced by around 25,600m3.

Local and   regional flood modelling has shown that in major events under developed conditions, the peak
water level within the site is increased, but the impact on neighbouring areas is negligible. This is because
at the southern boundary of the site there is a sharp increase in surface levels, and so increases in flood
levels within the site do not extend upstream. The waterway corridor width at the southern boundary of the
site has also been widened to 190 metres, which is equal to the existing 100 year ARI flood width at this

point, so that local overland flow paths are not impeded.

Downstream of the site, the loss of flood storage within the site does not            impact on flood levels for
neighbouring         areas.   Lake Weyba covers an area of 997 hectares. The volume of flood storage available
between 2.09 mAHD (which is the current 100 year ARI regional flood level in Lake Weyba) and 0.36 mAHD

(which is the MHWS level at Munna Point) is approximately 17,250,000m3. There is also significant
additional flood storage in the surrounding flood-plain areas. Therefore the loss of flood storage within the
site is minor when compared to the surrounding flood-plain and Lake Weyba.

Ta ble 81  -           FI00d 5torage WI"thOIn L0t 11


         11m
                                              ~twl[lri                            I
             ~                                 ~
       (
       ffil) ~                                   ~
                                                                       ri1m:lmm   I
          3.00                 175,024           106,454                -68,571
          2.75                 138,102           86,054                 -52,048
          2.50                 105,537           67,913                 -37,624
          2.25                 77,041            51,425                 -25,616
          2.00                 52,515            36,422                 -16,093
          1.75                 31,558            22,985                 -8,573
          1.50                  14,689           11,563                 -3,127
          1.25                  4,406             3,695                  -711

          1.00                   422              342                     -80

          0.75                    4                 1                     -3

          0.50                    0                 0                      0




Compensatory excavation within the site has not been proposed due to the potential environmental impacts.
It was considered beneficial to preserve the existing waterway and vegetation through Lot 11 in its current
state.  Flood modelling has shown that compensatory excavation is not required for flood alleviation

purposes.

It is noted that the Noosa Council Strategic Plan (1995)states that: "filling of areas other than the designated
Urban Area is not acceptable.            Therefore, rural township development and rural residential development
which occurs beyond the Urban Area should not involve filling of the floodplain". The filling proposed within
Lot 11 is located within the previous Maroochy Shire Council and therefore is not covered          by the Noosa
Council Strategic Plan. In addition, the Noosa River flood modelling that was conducted in Mike 11, which
was used       to inform the Strategic Plan, did not include Keyser Creek as flood storage as the model sections
did not extend across Lot 11.

The Sunshine Coast Regional Council Growth Management Position Paper (SCRC 2008) states that "new
urban development is avoided in flood prone areas and floodplains unless there is compelling justification
that demonstrates overriding community benefits and that any negative impacts resulting from development
can   be appropriately and sustainably managed." The question of whether this proposed development can
constitute an overriding community benefit is beyond the scope of this report.         This report will determine




Northbrook Corporation Pty Ltd                             Version 1                               23 October 2012
Flood Study v1.doc                                Commercial in Confidence                                Page 24

Used in these records

About this file

File size
93.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 8 of 37 Appendix 6 - Flood Study MCU12_0208.pdf · 93.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.