 “Adamson Town Planning, specialising in providing higher order town planning advice”




Works application. This includes requirements in addition to those provided in the Concept –
Construction and Tree Management Plan.

Information Required

    3. Please provide a Preliminary Construction Management Plan addressing all
       requirements outlined in Advisory note 11 of the final Judgment (Appeal No. 3746 of
       2023).

Response:

The applicant has provided a Construction Management Plan for the development, which is
directly related to the operational works for selected tree clearing only and will be undertaken
by Biodiverse Environmental (refer Attachment 3). It is intended to provide another CMP for
the construction of the eco-cabins, including a Traffic Management Plan consistent with
Manual of Uniform Traffic Control Devices (MUTCD). The traffic management for the tree
clearing is to occur in accordance with Appendix 3 – Pedestrian and Traffic Management Plan.

It is suggested that a full Traffic Management Plan (MUTCD) is not required for the tree clearing
component, which is to occur wholly within the site, with access to the operational area well
removed from Noosa Drive. The tree clearing works can be readily managed within the
proposed parking area for the eco-cabins to prevent any offsite traffic impacts with work also
occurring over a relatively short period.

General Advice

Item – Performance bonds (condition 20)

In accordance with condition 20 of the final Judgment (Appeal No. 3746 of 2023), a performance
bond is required prior to the issue of a Development Permit or Operational Works.

Advice

    1. Security in the form of a cash bond or trading bank guarantee to the sum outlined in the
       final Judgment (Appeal No. 3746 of 2023), must be submitted to Council. It is noted that
       this condition must be satisfied prior to the issue of the subject Operational Works
       approval for vegetation clearing.

Response:

The applicant will be providing the bond as required by the development approval prior to the
issue of the development permit for operational works. It is expected that bond will be lodged
as soon as possible.



                                                                                        3|Page
18006 – RACV Noosa Resort, Operational Works (Tree Clearing)

Used in these records

About this file

File size
293 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Letter to NC - Response to information request.pdf · 293 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.